Viewpoint: Lawyer as Constructor
A long time ago, when I was a young project manager, I had the temerity to complain that accountants were trying to run my job. As a professional engineer, I believed my technical education and abilities counted for more than theirs should on the construction site.
However, I was confident that I knew how best to manage my own project and, therefore, had the confidence to proceed accordingly.
![]() |
WELLS |
Construction of the Pentagon started on Sept. 11, 1941, and ended on January 15, 1943. The two months it took for site selection, preliminary design and federal appropriations brought the total project time to 18 months.
Construction of the 2.3-million-sq-ft office building known as Four World Trade Center—the first post-9/11 building to top out on the original World Trade Center site—is now slated to open this fall, some 144 months after 9/11.
At that production rate—16,000 sq ft per month—the 6.6-million- sq-ft Pentagon would have finished 30 years after World War II ended!
Imagine what today's attorneys would have advised the roofing subcontractor to do when he learned that his work on the roof of the fourth floor of the Pentagon had to be torn out because a fifth floor had been added to the structure.
However, the effect on the project of that theoretical delay-and-disruption claim would have paled beside the multiyear legal battle that would have ensued from President Franklin D. Roosevelt's last-minute decision to switch from the original site to the Potomac River floodplain, where the Pentagon stands today.
Those and a host of other opportunities to litigate may not have pushed the Pentagon's completion date to 1975, but they surely would have significantly delayed both the start and finish of that job.
Down a Slippery Slope
These two projects, of course, are far from comparable. The multitudes of political and jurisdictional challenges that had to be successfully navigated to bring the Four World Trade Center project to fruition would be no doubt incomprehensible to the Pentagon's master builders.
Nonetheless, comparing them—one with architects and engineers in charge, the other with attorneys calling the shots—does say something about where the American construction industry has gone in the past 75 years.
If that Pentagon roofer had a good construction lawyer in 1942, it's likely he would have been the only one who did. Had he been so inclined, he probably could have run roughshod over everyone else on his way from the construction site to the courthouse and the bank.
But it might not have been so simple the next time, because everyone else would have started looking for his or her own construction lawyer.
It's like the old "Spy vs. Spy" paradigm in Mad magazine: To prevail, one must continually raise the bar, always building upon and adding to whatever worked before, making expensive, time-consuming escalation imperative.
Role Reversal
By their reluctant embrace of that attorney-driven process over the years, architects and engineers have unwittingly transferred their traditional control of the construction process to their attorneys—so much so that, today, they dare not make a move without them.
Originally an adjunct to the construction industry, construction law has become a sophisticated, highly complex industry in its own right. The practice has grown so much that it can be characterized as the tail that wags the dog.
As if there weren't sufficient risks already inherent in the business of bending nature to our will, we have added a new, highly potent risk: The risk that the other party to our contract has better lawyers than we do. Is the American construction industry better off for that? I think not.
Walter J. "Johnny" Wells Jr., P.E., is a self-styled construction management consultant with 40 years of varied national and international construction experience. You can contact Wells at his Wesley Chapel, Fla., office by calling 813-416-0357. His email address is jwells1965@gmail.com.
This is a very well done article, and timely. I think Wells makes a great point here about lawyers in the construction industry - has the page turned whereby lawyers are actually runnin...
What is perhaps missing from the piece is questions about how we actually got to this point? Whose fault is it, for example? The contractors? The lawyers? The system?
Another missing point is who is benefiting from this shift?
To answer both questions I feel like there is a very good argument that this problem was actually created by the construction industry. Large well-funded companies love the litigation environment because it can become a profit center for them when pitted against smaller and less-funded opponents.
The legal system is a broken system. It's very broken, and if the construction industry wants to jump into that system and weave it into their own industry, it's going to be a similar fate.
Scott makes some excellent points. Another factor to consider is that the Pentagon was constructed with a cost-plus contract under war-time conditions that demanded extraordinary sacri...
I enjoyed this article and found it very relevant to a discussion of a broader subject: are "we" just not as good as we used to be? As a whole industry? <br/><br/>I tend to think this i...
I tend to think this is not the case, but is at least partially responsible for the "lawyer-ing up" of most firms in the industry. As buildings have become increasingly complex in design, function, context of surroundings, and most importantly - financial backing, the role of lawyers in the industry has paralleled. Similarly, as Engineers, Architects, Builders, and any other professional in this industry suffers from the inflated education system which primes them for this industry (i.e. 7 years to become an Architect, 4 of which are spent arguing "theory", and 3 of which are spent detailing wall sections in CAD) the only real defense against risk related to lacking professional ability is in the form of a law firm to have our backs. Any discussion of a productive, efficient, and complex future in the building industry must include the objective analysis of when and when-not to have a lawyer involved with typical dealings. Sometimes, things take longer because it's necessary, is 11 years necessary for the 4 World Trade Center building necessary? It depends on the context, I believe.
It is a little disingenuous to suggest that attorney involvement sends Contractors to the "Bank" and that they are making money off of attorney involvement. Clients are being either pr...
Thanks to mchapman for your excellent and well-researched response. I would be interested in knowing whether the many accident victims in the horribly low-safety construction environmen...
One hundred years ago it was already common for lawyers to create problems for engineers.<br/><br/>For example in the July 24, 1915 issue of "Engineering Record" in an editorial titled"...
For example in the July 24, 1915 issue of "Engineering Record" in an editorial titled"Leaving Lawyers out" it was noted that it took just 45 minutes for Chicago city engineers and engineers of the Chicago and Northwestern Railway to come to an agreement on adjusting the costs of the Franklin Street bridge improvements due to the insistence of the Commissioner of public works that lawyers be debarred
from the negotiations.
"The president,backed by his engineers,knew what was a fair bargain, and the adjustment, therefore came quickly without the quibbling and technical legal persiflage with which lawyers are wont to clothe negotiations. Many another engineering problem would be well on the way to solution were the opposing engineers left to agree upon the facts and adjust differences of opinion between themselves instead of intrusting the negotiations to lawyers with little appreciation of the engineering features of the problem"