April 2017
Related Article:
Hot Construction Market Shows No Signs of Slowing
Click below for earlier editions:
2015
Rank |
Project/Location |
Project Costs ($ Mil.) |
Start/End Dates |
Owner |
Team |
---|---|---|---|---|---|
1
|
LOS ANGELES STADIUM AT HOLLYWOOD PARK Inglewood, Calif. |
$2,600
|
Nov. 2016
Aug. 2019 |
Hollywood Park Land Co. |
Designer: HKS Inc. Contractor: Turner/AECOM |
2
|
CENTURY PLAZA REDEVELOPMENT Century City, Calif. |
$2,500
|
Dec. 2016
March 2019 |
Woodridge Capital LLC
|
Designer: Pei Cobb Freed & Partners;
Gensler; HED Architects
Contractor: Webcor Builders |
3
|
MID-COAST CORRIDOR TRANSIT PROJECT San Diego |
$1,700
|
Fall 2016
2021 |
SANDAG-Contracts & Procurement
|
CM/GC: Mid-Coast Transit Constructors, a
Joint Venture of Stacy & Witbeck Inc.,
Skanska USA and Herzog Contracting
Corp.
|
4
|
OCEANWIDE CENTER San Francisco |
$1,600
|
Dec. 2016
2021 |
Oceanwide Holdings
|
Designer: Foster + Partners; Heller
Manus Architects
Contractor: Swinerton/Webcor JV |
5
|
LLUMC CAMPUS TRANSFORMATION PROJECT Loma Linda, Calif. |
$1,400
|
Spring 2016
2020 |
Loma Linda University
|
Designer: NBBJ
Contractor: McCarthy Building Cos. |
6
|
CHEVRON RICHMOND REFINERY MODERNIZATION Richmond, Calif. |
$985
|
Dec. 2016
Dec. 2018 |
Chevron Richmond
|
EPC: Chevron Richmond
|
7
|
CALIFORNIA FLATS SOLAR POWER FACILITY Monterey County, Calif. |
$850
|
Jan. 2016
2018 |
California Flats Solar LLC
|
Designer: First Solar Inc.
Contractor: McCarthy Building Cos. |
8
|
MARIN GENERAL HOSPITAL REPLACEMENT Greenbrae, Calif. |
$535
|
July 2016
Mid-2020 |
Marin Healthcare District
|
Designer: Lee Burkhart Liu Inc./Perkins
Eastman
Contractor: McCarthy Building Cos. |
9
|
NEW LONG BEACH CIVIC CENTER Long Beach, Calif. |
$520
|
July 2016
2019 |
Plenary-Edgemoor Civic Partners; City
of Long Beach
|
Designer: SOM | Skidmore, Owings &
Merrill LLP
Contractor: Clark Construction Group |
10
|
BEVERLY CENTER RENOVATION Los Angeles |
$500
|
March 2016
Late 2018 |
Taubman Co.
|
Designer: Massimiliano Fuksas Architetto
Contractor: Jacobsen/Swinerton Construction |
10
|
MEXICAN MUSEUM AND RESIDENTIAL TOWER San Francisco |
$500
|
March 2016
March 2019 |
The Mexican Museum
|
Designer: Handel & Associates Architects
Contractor: Webcor Builders |
10
|
STAR WARS LAND DISNEYLAND Anaheim |
$500
|
April 2016
2019 |
Walt Disney Co.
|
Designer: Walt Disney Imagineering
Contractor: Whiting-Turner Contracting Co. |
13
|
SAN FRANCISCO INTERNATIONAL AIRPORT TERMINAL
1 BOARDING AREA B RECONSTRUCTION San Francisco |
$477
|
Dec. 2016
July 2020 |
City & County of San Francisco
Airports Commission
|
Designer: Gensler
Contractor: Austin Webcor JV |
14
|
TRANSBAY 8
San Francisco |
$465 |
Aug. 2016
Feb. 2020 |
Related Cos. of California
|
Designer: OMA/Rem Koolhaas and
Fougeron Architecture
Contractor: Webcor Builders |
15
|
CALIFORNIA HIGH-SPEED RAIL CONSTRUCTION
PACKAGE 4 Kern & Tulare Counties, Calif. |
$444
|
Sept. 2016
June 2019 |
California High Speed Rail Authority
|
Design-Build: California Rail Builders LLC
|
16
|
SAN FRANCISCO INTERNATIONAL AIRPORT TERMINAL
1 CENTER RENOVATION San Francisco |
$442
|
Sept. 2016
Late 2022 |
City & County of San Francisco
Airports Commission
|
Designer: Gensler
Contractor: Hensel Phelps Construction Co. |
17
|
ECHOWATER BIOLOGICAL NUTRIENT REMOVAL/
PRIMARY EFFLUENT PUMPING STATION Elk Grove, Calif. |
$415
|
Aug. 2016
May 2021 |
County of Sacramento
|
Designer: Black & Veatch (BNR); CH2M
(PEPS)
Contractor: Dragados USA Inc. |
18
|
1120 S GRAND SOUTH PARK PHASE 2 Los Angeles |
$375
|
Aug. 2016
2019 |
Mack Urban; AECOM
|
Designer: A.C. Martin/Togawa Smith
Martin
Contractor: Tishman Construction Corp. |
19
|
KAHULUI AIRPORT CONSOLIDATED CAR RENTAL
FACILITY Kahului, Hawaii |
$340
|
April 2016
Late 2019 |
Dept. of Transportation - Airports
Division
|
Designer: Demattei Wong Architecture
Contractor: Hawaiian Dredging Construction Co. |
20
|
MOFFETT TOWERS II Sunnyvale, Calif. |
$338
|
Aug. 2016
Q3 2018 |
Jay Paul Co.
|
Designer: DES Architects + Engineers
Contractor: Level 10 Construction |
21
|
HONOLULU AIRPORT CONSOLIDATED CAR RENTAL
FACILITY Honolulu |
$315
|
Oct. 2016
2020 |
State of Hawaii Dept. of Transportation
|
Designer: Demattei Wong Architecture Inc.
Contractor: Watts Constructors |
22
|
SPRING STREET TOWERS Los Angeles |
$305
|
Jan. 2016
June 2018 |
Holland Partner Group; North
American Sekisui House LLC
|
Designer: MVE + Partners
Contractor: Holland Construction |
23
|
200-MW TULE WIND POWER PROJECT Boulevard, Calif. |
$300
|
Oct. 2016
Late 2017 |
Avangrid Renewables
|
Designer: Avangrid Renewables
Contractor: Tule Wind LLC |
23
|
ONNI RESIDENTIAL TOWER Los Angeles |
$300
|
April 2016
May 2018 |
ONNI Group
|
Designer: Chris Dikeakos Architects Inc.
Contractor: ONNI Group |
23
|
SANTA CLARA SQUARE APARTMENTS Santa Clara, Calif. |
$300
|
Dec. 2016
2020 |
The Irvine Co.
|
Designer: MVE + Partners
Contractor: Western National Contractors |
26
|
I-5 NORTH COAST EXPRESS LANES PROJECT San Diego County |
$298
|
Nov. 2016
2020 |
SANDAG - Contracts & Procurement
|
Design-Build: Flatiron-Skanska-Stacy
and Witbeck, a Joint Venture
|
27
|
PECHANGA RESORT & CASINO EXPANSION Temecula, Calif. |
$285
|
Jan. 2016
Dec. 2017 |
Pechanga Band of Luiseno Indians
|
Designer: Delawie
Contractor: Tutor Perini Building Corp. |
28
|
160 FOLSOM San Francisco |
$270
|
Late 2016
Late 2019 |
Tishman Speyer Properties
|
Designer: Studio Gang Architects
Contractor: Lendlease |
29
|
FIVE LAGUNAS RESIDENTIAL COMPLEX Laguna Hills, Calif. |
$260
|
Aug. 2016
Summer 2018 |
Merlone Geier Partners
|
Designer: Architects Orange
Contractor: C.W. Driver |
30
|
STANFORD CHEM-H AND NEUROSCIENCES INSTITUTE
BUILDING Palo Alto, Calif. |
$252
|
Fall 2017
April 2019 |
Stanford University
|
Designer: Ennead Architects
Contractor: Whiting-Turner |