The Top Specialty Contractors list, published annually, ranks the general contractors, both publicly and privately held, based on construction contracting-specific revenue.
More Information On Top Speciality Contractors By Sectors:
View Top Specialty Contractors By Sectors
Related Article:
Regional Revenue Grows As Contractors Enjoy Rebound
Rank 2016/2015 |
Company / Location / Website /
Top Officer |
Largest Project to Break Ground its Location Project Value ($ Mil.) |
Market Sectors By % of Revenue |
Regional Rev. 2015 ($ Mil)** |
|
---|---|---|---|---|---|
1/14 |
HUNT CONSTRUCTION GROUP, AN AECOM COMPANY*
Phoenix | huntconstructiongroup.com Robert F. Hart, Executive Vice President & Division Manager |
ASU Sun Devil Stadium Reinvention Tempe, Ariz. 187.00 |
90 General Building 10 Transportation |
528.27 |
|
2/3 |
LAS VEGAS PAVING CORP.
Las Vegas | lasvegaspaving.com Robert L. Mendenhall, CEO |
I-11 Boulder City Bypass Las Vegas 235.00 |
100 Transportation |
486.00 |
|
3/4 |
MCCARTHY BUILDING COS.
Phoenix | mccarthy.com Bo Calbert, Southwest Region President |
Chandler Ocotillo Water Reclamation Facility Chandler, Ariz. 135.28 |
73 General Building 19 Power 6 Transportation |
351.05 |
|
4/2 |
SUNDT CONSTRUCTION INC.*
Tempe, Ariz. | sundt.com Ryan Abbott, Southwest District Manager, Senior Vice President |
Banner University Medical Center Tucson Tucson 260.00 |
61 General Building 23 Transportation 12 Industrial Process |
314.45 |
|
5/5 |
THE PENTA BUILDING GROUP
Las Vegas | pentabldggroup.com Jeff Ehret, President |
Lucky Dragon Hotel and Casino Las Vegas Not Provided |
100 General Building |
298.15 |
|
6/7 |
KITCHELL CORP.
Phoenix | kitchell.com James T. Swanson, President |
Salt River Pima-Maricopa Indian Community
Justice Center Scottsdale, Ariz. 40.00 |
99 General Building |
268.10 |
|
7/8 |
GRANITE CONSTRUCTION INC.
Tucson | graniteconstruction.com Todd Keller, Vice President, Arizona Region |
Not Provided |
63 Transportation 31 Other Project Types 3 Power |
248.73 |
|
8/6 |
CHANEN CONSTRUCTION CO.
Phoenix | chanen.com Steven R. Chanen, President & CEO |
Not Provided |
100 General Building |
217.54 |
|
9/23 |
DPR CONSTRUCTION
Phoenix | dpr.com Derek Kirkland, Business Unit Leader |
Confidential Project Chandler, Ariz. 25.02 |
73 General Building 24 Telecommunications 1 Industrial Process |
207.11 |
|
10/1 |
KIEWIT CORP.
Phoenix | kiewit.com Bruce Grewcock, CEO |
Project Neon Las Vegas 554.00 |
62 Transportation 21 General Building 9 Water Supply |
188.74 |
|
11/— |
Q&D CONSTRUCTION INC.
Sparks, Nev. | qdconstruction.com Norman Dianda, President |
EL Wiegand Fitness Center Reno, Nev. 38.50 |
52 Transportation 32 General Building 7 Manufacturing |
182.71 | |
12/12 |
BRADBURY STAMM CONSTRUCTION INC.
Albuquerque | bradburystamm.com Cynthia K. Schultz, CEO |
Carlsbad Elementary School Carlsbad, N.M. 41.65 |
100 General Building |
181.32 |
|
13/16 |
THE JAYNES COS.
Albuquerque | jaynescorp.com Rick Marquardt, CEO & Chairman |
Taos Ski Valley Resort Expansion Taos, N.M. Not Provided |
100 General Building |
175.10 |
|
14/11 |
OKLAND CONSTRUCTION CO.*
Tempe, Ariz. | okland.com William Okland, President |
American Campus - Arizona State University
Student Housing Tempe, Ariz. 89.00 |
91 General Building 9 Transportation |
170.60 | |
15/10 |
MARTIN-HARRIS CONSTRUCTION
Las Vegas | martinharris.com Frank Martin, President |
Legacy House at Centennial Hills Las Vegas 15.00 |
57 General Building 21 Manufacturing 11 Telecommunications | 165.56 | |
16/15 |
HAYDON BUILDING CORP.
Phoenix | haydonbc.com Gary T. Haydon, President |
US-60 & SR-303L Interim Traffic Interchange Phoenix Not Provided |
70 General Building 23 Transportation 5 Sewerage/Solid Waste | 160.83 |
|
17/— |
FNF CONSTRUCTION INC.*
Tempe, Ariz. | fnfinc.com Jed Billings, CEO |
US-60 Silver King and Superior Streets Superior, Ariz. 33.24 |
100 Transportation |
151.37 |
|
18/— |
THE WEITZ CO.
Phoenix | weitz.com Chris Harrison, Executive Vice President, Southwest Office President |
Hacienda at the River Tucson 20.88 |
52 General Building 47 Transportation 1 Interior/Tenant Improvements |
132.89 | |
19/18 |
THE WHITING-TURNER CONTRACTING CO.
Las Vegas | whiting-turner.com Paul Schmitt, Senior Vice President |
The Motley Tempe, Ariz. Not provided |
88 General Building 11 Industrial Process 1 Transportation |
125.89 | |
20/25 |
BALFOUR BEATTY US
Dallas | balfourbeattyus.com Mark Layman, Chairman & CEO |
Mountain Shadows Resort Paradise Valley, Ariz. 38.23 |
100 General Building |
121.39 | |
21/28 |
HARDISON/DOWNEY CONSTRUCTION
Phoenix | hardisondowney.com Pat Downey, President |
North Roosevelt Apartments Phoenix 34.96 |
93 General Building 7 Interior/Tenant Improvements |
120.35 | |
22/34 |
LAYTON CONSTRUCTION CO. LLC
Phoenix | laytonconstruction.com Andrew Geier, Executive Vice President |
Home Goods Distribution Center Tucson Not Provided |
97 General Building 3 Other Project Types |
112.30 | |
23/9 |
ARCHER WESTERN CONTRACTORS
Phoenix | walshgroup.com Matthew Walsh, Co-Chairman |
Morenci Water Treatment Plant Expansion Morenci, Ariz. 5.71 |
73 General Building 19 Sewerage/Solid Waste 5 Water Supply |
102.08 | |
24/19 |
AMES CONSTRUCTION INC.*
Scottsdale, Ariz. | amesconstruction.com John Ames, Regional President |
Not Provided |
70 Other Project Types 30 Transportation |
100.00 | |
25/36 |
PCL CONSTRUCTION INC.*
Phoenix | PCL.com Tom O'Donnell, Regional Vice President |
Union Hills Water Treatment Plant Solids Handling
Improvements Phoenix 21.92 |
97 Water Supply 3 Power |
93.95 | |
26/31 |
SKANSKA USA
Phoenix | usa.skanska.com Ross Vroman, Executive Vice President & General Manager |
Aligned Data Center Phoenix 26.00 |
23 Other Project Types 23 Sewerage/Solid Waste 22 Transportation |
79.02 | |
27/— |
DCK WORLDWIDE LLC
Phoenix | dckww.com Brian T. Contino, Senior Vice President & General Manager |
enHance Park @ 2nd and Moreland Multifamily
Complex - Phase 1 of 3 Phoenix 9.00 |
100 General Building |
75.99 | |
28/— |
BURKE CONSTRUCTION GROUP INC.*
Las Vegas | burkecgi.com Kevin E. Burke, President & CEO |
Bed Bath & Beyond Harmon Distribution Center Las Vegas 5.34 |
81 General Building 19 Interior/Tenant Improvements |
67.96 | |
29/— |
FANN CONTRACTING INC.
Prescott, Ariz. | fanncontracting.com Michael Fann, President |
ADOT I-10 Hovatter Road Salome, Ariz. 8.58 |
68 Transportation 22 Master-Planned Development/ Site Infrastructure 10 Sewerage/Solid Waste |
66.30 | |
30/— |
MARKHAM CONTRACTING CO.
Phoenix | markhamcontracting.com Michael F. Markham Sr., President |
Magee Road Improvements Tucson 8.68 |
50 Transportation 27 Master-Planned Development/ Site Infrastructure 23 General Building |
64.16 | |
31/26 |
HOLDER CONSTRUCTION CO.
Phoenix | holderconstruction.com Bill Headley, Senior Vice President |
Not Provided |
59 General Building 24 Telecommunications 18 Interior/Tenant Improvements |
61.50 | |
32/27 |
O’NEIL INDUSTRIES INC./W.E. O’NEIL CONSTRUCTION CO.
Phoenix and Tucson | weoneil.com John Hobbs and Scott Dombrowski, Presidents |
Arrowhead Towne Center Renovation Glendale, Ariz. 7.80 |
84 General Building 15 Manufacturing 1 Transportation |
59.90 | |
33/40 |
CSW CONTRACTORS INC.
Scottsdale, Ariz. | cswcontractors.com Robert Meyers, CEO |
Scottsdale National Golf Course Scottsdale, Ariz. 13.18 |
39 Power 36 Transportation 12 General Building |
57.23 |
|
34/17 |
HENSEL PHELPS
Phoenix | henselphelps.com Steve M. Grauer, Vice President, District Manager |
Luhrs Marriott Courtyard / Residence Inn Phoenix 51.27 |
57 General Building 43 Transportation |
54.57 | |
35/29 |
MORTENSON CONSTRUCTION
Chandler, Ariz. | mortenson.com Robert Nartonis, Senior Vice President |
Confidential Project Arizona Not provided |
98 General Building 2 Power |
52.39 | |
36/— |
KLINGER CONSTRUCTORS LLC
Albuquerque | klingerllc.com Tom Novak, CEO |
Heritage Hotels & Resort Albuquerque 25.00 |
79 General Building 20 Industrial Process 1 Manufacturing |
48.82 | |
37/38 |
KINNEY CONSTRUCTION SERVICES INC. (KCS)
Flagstaff, Ariz. | kinneyconstruction.net Tim Kinney, President & CEO |
Northern Arizona University International Pavilion Flagstaff, Ariz. 4.80 |
67 General Building 12 Water Supply 8 Transportation |
48.13 | |
38/52 |
AUSTIN COMMERCIAL
Phoenix | austin-ind.com Jim Lauer, Regional Project Manager |
Not Provided |
86 Transportation 14 General Building |
44.07 | |
39/50 |
ZACHRY GROUP
Page, Ariz. | zachrygroup.com Steve Brauer, President, Industrial Services Group |
Not Provided |
52 Petroleum 48 Power |
42.21 | |
40/13 |
VCC LLC
Tempe, Ariz. | vccusa.com Don Davis, Senior Vice President |
Dicks at Meadowood Reno, Nev. 0.19 |
100 General Building |
41.30 | |
41/45 |
CALIENTE CONSTRUCTION INC.
Tempe, Ariz. | calienteconstruction.com Lorraine Bergman, President & CEO |
AT&T Phoenix Main SES Phoenix 12.00 |
47 Telecommunications 45 General Building 8 Other Project Types | 39.00 | |
42/37 |
ALBERICI-FLINTCO
Albuquerque | alberici.com Peter Kozicz, President & CEO |
Devon Energy Field Office Expansion Artesia, N.M. 6.70 |
99 General Building 1 Industrial Process | 37.37 | |
43/42 |
TURNER CONSTRUCTION CO.
Phoenix | turnerconstruction.com Richard C. Bach, Senior Vice President |
Henderson Valley Hospital Henderson, Nev. 173.00 |
57 Manufacturing 43 General Building | 37.00 | |
44/47 |
WHITE SANDS CONSTRUCTION INC.
Alamogordo, N.M. | whitesandsconstruction.com McChristie Curry, Vice President |
East Mesa Public Safety Complex Las Cruces, N.M. 10.39 |
96 General Building 4 Interior/Tenant Improvements |
32.90 | |
45/51 |
THE KORTE CO.
Las Vegas | korteco.com Greg Korte, President |
Summerlin Village 20 Community Park Las Vegas 5.47 |
100 General Building |
31.31 | |
46/50 |
JE DUNN CONSTRUCTION GROUP
Tempe, Ariz. | jedunn.com Benjamin Strobl, Vice President |
USACE AMFS Medical MATOC Cannon AFB Medical
and Dental Clinic Replacement Hospital Cannon AFB, N.M. 53.79 |
100 General Building |
28.90 | |
47/49 |
GARNEY HOLDING CO.
Tempe, Ariz. | garney.com Wayne O'Brien, Chief Operating Officer |
Central Arizona Project Surface Water Treatment
Plant Apache Junction, Ariz. 9.21 |
97 Water Supply 3 Sewerage/Solid Waste |
27.32 |
|
48/— |
LLOYD CONSTRUCTION CO.*
Tucson | lloydconstruction.com William E. Lloyd, President |
New Vail Elementary School Corona de Tucson, Ariz. 9.50 |
100 General Building |
26.30 | |
49/— |
RSG BUILDERS LLC
Phoenix | rsgbuilders.com Craig Zupancic, Managing Principal |
Zog Digital Phoenix, Ariz. 1.13 |
100 General Building |
14.28 | |
50/56 |
MC CONSTRUCTION MANAGEMENT INC.
Cave Creek, Ariz. | mcbuilders.net Jim McClymonds, President |
Not Provided | 64 General Building 36 Interior/Tenant Improvements |
11.00 | |
*REVENUE WAS PROVIDED ON A FISCAL-YEAR BASIS. ALL OTHERS PROVIDED CALENDAR-YEAR DATA, WHICH IS PREFERRED. **INCLUDES REVENUE GENERATED FROM GENERAL CONTRACTING, DESIGN-BUILD AND CONSTRUCTION MANAGEMENT AT-RISK AS WELL AS FEES FROM PROGRAM MANAGEMENT AND CONSTRUCTION MANAGEMENT FOR FEE. |
Copyright ©2024. All Rights Reserved BNP Media.
Design, CMS, Hosting & Web Development :: ePublishing