Related Articles: |
Rank | Project/Location | Project Cost ($ mil.) | Start Date/ End Date | Owner/Prime Contractor |
---|---|---|---|---|
1 |
Brunswick County Power Station Brunswick County, Va. | 1,200 | Sept. 2013 Summer 2016 | Owner Dominion Virginia Power EPC Contractor Fluor |
2 |
Panda Liberty Generation Plant Bradford County, Pa. | 800+ | Aug. 2013 Early 2016 | Owner Panda Power FundsEPC Contractor Gemma-Lane |
2 |
Panda Patriot Generation Plant Lycoming County, Pa. | 800+ | Aug. 2013 Mid-2016 | Owner Panda Power FundsEPC Contractor Gemma-Lane |
4 |
High Performance Computing Center 2 Fort Meade, Md. | 792 | May 2013 Summer 2015 | Owner U.S. Army Corps of Engineers, Baltimore District Design-Build Contractor Hensel Phelps/Kiewit |
5 |
Enhanced Nutrient Removal Process Back River Wastewater Treatment Plant Baltimore | 560 | Oct. 2013 Late 2017 | Owner City of Baltimore Dept. of Public Works Designer Whitman, Requardt & Associates; KCI General Contractor Archer Western Contractors Ltd. |
6 |
Baltimore Horseshoe Casino With Garage Baltimore | 400 | May 2013 Fall 2014 | Owner-Builder/Developer Caesars Entertainment/Harrah’s Corporate Office Architect Friedmutter Group General Contractor Whiting-Turner Contracting Co. |
7 |
Reading Hospital, 7th Avenue Building West Reading, Pa. | 354 | Sept. 2013 Fall 2016 | Owner Reading Hospital & Medical CenterDesigner BallingerCM/General Contractor LF Driscoll Co. |
8 |
Dominion Blvd. Improvements, Replacement Bridge Chesapeake, Va. | 345.2 | Jan. 2013 Early 2017 | Owner City of Chesapeake, Va. Lead Engineer Parsons Brinckerhoff Joint Venture Dominion Boulevard Constructors JV (McLean Contracting; Bryant Contracting; R.R. Dawson Bridge; and E.V. Williams) |
9 |
FMC Tower at Cira Centre South Philadelphia | 341 | Summer 2013 June 2016 | Owner Brandywine Realty Trust Architect Erdy McHenry Architecture; Pelli/Bower Lewis Thrower CM Tutor Perini Corp. |
10 |
University of Maryland Health Sciences Research Facility Phase III Baltimore | 305.4 | Sept. 2013 Aug. 2016 | Owner University of Maryland, Baltimore Architect Design Collective Architects; HOKCM Barton Malow Co. |
11 |
Garrison Energy Center Dover, Del. | 300 | June 2013 Summer 2015 | Owner Calpine Corp. EPC Contractor Kvaerner North American Construction |
12 |
Turnkey Propane Terminal and De-Ethanizer Facility Marcus Hook, Pa. | 270 | 3Q 2013 Not disclosed | Owner Sunoco EPC Contractor CB&I |
13 |
Anacostia River Tunnel Washington, D.C. | 253.9 | Nov. 2013 Nov. 2017 | Owner DC Water Lead Engineer Parsons Contractor Impregilo-Healy-Parsons JV |
14 |
Tunnel Dewatering Pump Station and Enhanced Clarification Facility Washington, D.C. | 251.4 | Aug. 2013 Nov. 2017 | Owner DC Water Lead Engineer CDM Contractor PC Construction |
15 |
International Monetary Fund HQ 1 Renewal Washington, D.C. | 250 | May 2013 Dec. 2016 | Owner International Monetary Fund Architect Skidmore, Owings & Merrill General Contractor Grunley Construction |
16 |
The New Sibley [Sibley Memorial Hospital] Washington, D.C. | 242 | July 2013 Aug. 2016 | Owner Johns Hopkins Medicine Architect Wilmot Sanz General Contractor Turner Construction |
17 |
I-95 Reconstruction at Girard Avenue Interchange (SR95 GR3) Philadelphia | 211.8 | Dec. 2013 July 2018 | Owner PennDOT Designer URS Contractor James J. Anderson Construction |
18 |
Metropolitan Park 4/5 Arlington, Va. | 160.1 | Dec. 2013 August 2016 | Owner Vornado Designer Torti Gallas Urban Contractor Balfour Beatty |
19 |
First Street Tunnel Washington, D.C. | 157.6 | Oct. 2013 March 2016 | Owner DC Water Designer Parsons Brinckerhoff Contractor Skanska/JayDee JV |
20 |
Celanese Plant, Boiler Replacement Narrows, Va. | 150 | June 2013 Early 2015 | Owner Celanese Corp. General Contractor Overland Contracting Engineer Black & Veatch |