Rank | Project | Location | Project Cost ($ mil.) | Start Date/ End Date | Owner/Contractor/Designer |
---|---|---|---|---|---|
1 | New Santa Clara Stadium | Santa Clara | $1,000 | June 2012 March 2016 |
Owner: Santa Clara Stadium Authority GC: Turner/Devcon, Joint Venture Design: HNTB Corp. |
2 | The Carlsbad Desalination Project | Carlsbad | $901 | Dec. 2012 June 2014 |
Owner: Poseidon Resources Inc. GC: Kiewit Shea Desalination (Kiewit Infrastructure West and J.F. Shea Co. JV) Design: IDE Technologies; ARCADIS; Tetra Tech |
3 | Graton Resort & Casino | Rohnert Park | $800 | June 2012 Late 2013 |
Owner: Federated Indians of Graton Rancheria/Station Casinos LLC GC: Tutor Perini Building Corp.; Rudolph and Sletten Design: KGA Architecture |
4 | BART Silicon Valley Berryessa Extension - Line, Track, Stations & Systems | San Jose | $772 | April 2012 March 2016 |
Owner: Santa Clara Valley Transportation Authority GC: Skanska USA/Herzog Contracting/Shimmick Construction, Joint Venture Design: LAN/T.Y. Lin |
5 | UC San Diego Jacobs Medical Center | La Jolla | $700 | Jan. 2012 June 2016 |
Owner: UC San Diego Health System GC: Kitchell Design: Cannon Design |
6 | Expo Phase II Light Rail | Santa Monica/Los Angeles | $541.7 | Jan. 2012 Oct. 2015 |
Owner: Exposition Metro Line Construction Authority GC: Skanska-Rados JV Design: Parsons Brinckerhoff |
7 | Catalina Solar Power Project |
Kern County | $520 | May 2012 June 2013 |
Owner/Design: EDF Renewable Energy GC: Bechtel Group Inc. |
8 | Lucile Packard Children’s Hospital Expansion | Palo Alto | $510 | Nov. 2012 Jan. 2016 |
Owner: Stanford University Medical Center GC: DPR Construction Design: Perkins+Will; HGA Architects & Engineers |
9 | Foothill Extension Phase 2A Alignment | Pasadena | $486 | May 2012 Sept. 2015 |
Owner: Metro Gold Line Foothill Extension Authority GC: Foothill Transit Constructors (Kiewit-Parsons JV) Design: Parsons Transportation Group |
10 | The Village at Santa Monica Mixed-Use Complex | Santa Monica | $350 | Feb. 2012 Jan. 2014 |
Owner: Related California GC: Charles Pankow Builders Ltd. Design: Koning Eizenberg Architecture Inc. |
11 | San Gabriel Trench Grade Separation Project |
San Gabriel | $336.5 | July 2012 Winter 2017 |
Owner/Design: Alameda Corridor-East Construction Authority GC: Walsh Construction |
12 | BART Warm Springs Station Extension - Line, Track, Stations and System | Fremont | $299.1 | May 2012 May 2015 |
Owner: Bay Area Rapid Transit District GC: Warm Springs Constructors (Kiewit-Mass JV) Design: HNTB Corp. |
13 | Third St. Light Rail Phase 2 - TBM/Launch Box & Tunnel | San Francisco | $233.6 | Jan. 2012 Nov. 2014 |
Owner: San Francisco Municipal Transportation Agency GC: Barnard Construction Co. Design: PB/Telamon JV |
14 | San Diego County Women’s Detention Facility | Santee | $221.5 | Aug. 2012 Jan. 2016 |
Owner: County of San Diego GC: Balfour Beatty Construction Design: Kaplan McLaughlin Diaz; HMC |
15 | Lorenzo Apartments | Los Angeles | $221.4 | April 2012 Fall 2014 |
Owner/GC: G.H. Palmer Associates Design: Killefer Flammang Architects |
16 | Water Quality Control Plant Phase 1 Expansion | Riverside | $192.2 | Sept. 2012 March 2015 |
Owner: City of Riverside GC: PCL Construction Inc. Design: CDM Smith |
17 | Blvd 6200 Phase 1 | Hollywood | $190.4 | June 2012 Dec. 2014 |
Owner: Clarett West Development/ DLJ Real Estate Capital Partners GC: Benchmark Contractors Design: VTBS Architects |
18 | San Marcos High School Rebuild | San Marcos | $180 | April 2012 Jan. 2014 |
Owner: San Marcos Unified School District GC: Lusardi Construction Co. Design: LPA Inc. |
19 | 10th and Market | San Francisco | $169.9 | Jan. 2012 March 2014 |
Owner: Tenth and Market LLC GC: Swinerton Builders Design: Handel Architects |
20 | Hall of Justice Repair and Reuse Project | Los Angeles | $169.2 | March 2012 Jan. 2014 |
Owner: Los Angeles County Public Works Dept. GC: Clark Construction Group Design: AC Martin Partners |
21 | The Vermont Apartment Towers | Los Angeles | $169 | May 2012 July 2014 |
Owner: J.H. Snyder Development Co. GC: J.H. Snyder Contracting Inc. Design: The Jerde Partnership |
22 | San Francisco Public Safety Building | San Francisco | $164.5 | Jan. 2012 Summer 2014 |
Owner: City & County of San Francisco GC: Charles Pankow Builders Ltd. Design: HOK; Mark Cavagnero Associates |
23 | Palo Alto Medical Foundation San Carlos Center | San Carlos | $164 | May 2012 Nov. 2014 |
Owner: Palo Alto Medical Foundation GC: Skanska USA Design: NBBJ |
24 | Hyundai Motor Co. Headquarters Expansion | Fountain Valley | $150 | May 2012 Oct. 2013 |
Owner: Hyundai Motor America GC: Hyundai AMCO; McCarthy Building Cos. (garage) Design: Gensler |
24 | The Source | Buena Park | $150 | Oct. 2012 April 2014 |
Owner/GC: M&D Properties Inc. Design: BonTerra Consulting |
26 | Anaheim Regional Transportation Intermodal Center (ARTIC) | Anaheim | $130 | Sept. 2012 Nov. 2014 |
Owner: City of Anaheim; Orange County Transit Authority GC: Clark Construction Group Design: Parsons Brinckerhoff/HOK |
26 | San Mateo County Jail | Redwood City | $130 | Aug. 2012 Dec. 2014 |
Owner: San Mateo County GC: Sundt/Layton Joint Venture Design: HOK |
26 | The Broad Museum | Los Angeles | $130 | May 2012 Jan. 2014 |
Owner: The Broad Art Foundation GC: Matt Construction Design: Diller Scofidio + Renfro |
26 | One Rincon Hill - Tower Two | San Francisco | $130 | Sept. 2012 Aug. 2014 |
Owner: Urban West of San Diego GC: Webcor Builders Design: Solomon Cordwell Buenz & Associates Inc. |
30 | Harrah’s Rincon Casino Expansion – Phase 7 | Valley Center | $125 | Nov. 2012 March 2014 |
Owner: Rincon San Luiseno Band of Mission Indians GC: W.E. O’Neil Construction Co. of California Design: Friedmutter Group |
31 | California Health Care Facility DeWitt Nelson Corrections Annex (Package 3) | Stockton | $123 | Nov. 2012 2013 |
Owner: Calif. Dept. of Corrections & Rehabilitation GC: Hensel Phelps Design: HOK |
32 | Santa Ana Freeway (I-5) Reconstruct and Widen Freeway and Undercrossing | Norwalk | $120.8 | Dec. 2012 Nov. 2016 |
Owner: Caltrans GC: Security Paving Design: Caltrans |
33 | Los Angeles Marriott Hotel Complex | Los Angeles | $120 | April 2012 March 2014 |
Owner: AEG; Williams/Dame & Associates GC: Sodo Builders LLC Design: GBD Architects Inc. |
34 | Highway 101 Willits Bypass | Willits | $107.9 | Oct. 2012 Dec. 2015 |
Owner/Design: Caltrans GC: Flatiron & Desilva Gates Construction, Joint Venture |
35 | One Santa Fe Apartments | Los Angeles | $106.6 | Jan. 2012 Dec. 2014 |
Owner: The McGregor Co. GC: Bernards Design: Michael Maltzan Architecture |