• U.S. 550 Colona North 
Widening, passing lane, wildlife detection system. 1.5 miles. April to late August. $7 million, FASTER funded.



• U.S. 160 Cat Creek, west of Pagosa Springs (MM 130)
Intersection improvements. March through May. $1.07 million.



• U.S. 160 in Pagosa Springs
Culvert replacement. July through August. $672,607, FASTER funded.
 


• U.S. 550 Red Mountain Pass 
Rockfall work (phase 2), retaining wall repair. Rockfall is mile point 91, retaining wall is mile point 89.6, approximately 1.5 miles north of snowshed. May to June 1. $845,880 contract for rockfall work, $591,201 contract for retaining wall repairs, FASTER funded.
  


• S.H. 62 in Ridgway, Uncompahgre River
Bridge replacement. May through November, with possible 2013 work. $7.26 construction budget, FASTER funded.



• S.H. 145 Telluride South 
Resurfacing. 11.5 miles. April through September. $5.4 million.



• S.H. 145 Telluride
Intersection safety improvements (roundabout). September through October (season 1). $2.25 million construction budget, includes $900,000 from Town of Telluride, plus FASTER funding.



• S.H. 145 at S.H. 62 West of Telluride, Leopard Creek 
Bridge replacement. May to late 2012. $3.8 million contract (FASTER).



• S.H. 145 at Ophir 
Culvert replacement. August through October. $1.13 budget, FASTER funded.



• U.S. 160 Monte Vista to Alamosa 
Passing lane at MP 222.44 to 226.04 (about four miles), season 1. July through November. $10.6 million, FASTER funded.



• U.S. 285 North & South of Center 
Resurfacing between MP 60 and 77, 17 miles. May to mid-August. $6.26 million.