With work slated for completion by January, Reece Albert Inc. of Midland-San Angelo is working the $4-million rebuilding to repair Broadway, affecting 1.5 mi of that street’s portion of State Highway 115 from the SH 176-SH 115 West split to the traffic light at 7th Street East in Andrews.
The work includes construction of curb and gutter, placing ADA ramps to accommodate pedestrians with disabilities, a full rehabilitation of the roadway, and placing a concrete intersection at Broadway and Main. The time allotted for the project is 160 working days.