FM457 Swing Bridge Replacement (Matagorda Bridge)

Sargent, Texas

Award of Merit

OWNER/LEAD DESIGN FIRM: Texas Dept. of Transportation

GENERAL CONTRACTOR: Austin Bridge & Road

BRIDGE ALTERNATIVE DESIGN: Modjeski and Masters

GEOTECHNICAL DESIGN: PSI

SECOND GEOTECHNICAL DESIGN: Terracon

CONSTRUCTION MANAGEMENT: CivilCorp LLC

SUBCONTRACTORS: DSI (DYWIDAG-Systems International); Freyssinet Inc.; J&S Contractors; Lone Star Paving; Matagorda Construction; Webber LLC


The team replacing the FM 457  Swing Bridge over the Gulf Intercoastal Waterway faced hurdles ranging from active vessel traffic to erratic weather to limited space for heavy lifts. Daily troubleshooting helped push the $41.2-million, 27-month project forward. 

A detailed logistics plan, crane mats and truck mats helped the team overcome the challenges of the site’s soft soils. The tight space hindered the movement of large cranes, making heavy lifts more complex. 

swing bridge replacement

Photo by ABR / Molly Pope Aero Photo

The new bridge provides a 75-ft vertical clearance over the waterway and uses a corkscrew configuration to get traffic onto the bridge.