www.enr.com/articles/5338-danube-bridge-2-crossing-nears-completion

Danube Bridge 2 Crossing Nears Completion

April 9, 2013
Danube Bridge 2 Crossing Nears Completion

One of the largest bridges ever built over the Danube River will officially open between Bulgaria and Romania early next month after decades of planning and lengthy construction delays.

The 1,391-meter-long road-rail bridge project survived not only tough physical conditions but also the sometimes chaotic transition of the host countries from communism to membership in the European Union.

From near Calafat, Romania, the so-called Danube Bridge 2's cable-supported deck crosses three 180-m-wide navigations channels, with 115-m-long and 124-m-long side spans.

Seven 80-m-long and one 52-m-long concrete box girder spans complete the crossing to the Bulgarian abutment near Vidin, where the highway runs onto a long embankment. The railroad track splits from the road and continues for 400 m on a viaduct.

The main contractor, FCC Construcción, S.A., Madrid, is still putting the finishing touches on its imposing structure in time for the May 9 ribbon cutting by José Manuel Barroso, the European Commission president. The bridge was originally due for completion  in April 2010. 

Of the four main reasons for delay cited by FCC's project design manager, José Ignacio Díaz de Argote, three relate to bureaucracy. The fourth cause concerns the late discovery of poor ground conditions under embankments.

Disruption from permitting and legislation changes might be unusual in Western Europe, but it comes as little surprise to Vardaman Jones, a director of the London-based design firm High-Point Rendel.

Working with the French design firm Ingérop S.A., Courbevoie, High-Point Rendel oversees the project's design and construction for the Bulgarian Ministry of Transport, Information Technology and Communications.

Developing the project in a period of intense political and economic transition was “a huge task for the countries,” says Jones. For example, even when the Bulgarian government hired international engineers to produce bidding designs in 2003, matters of land ownership had yet to be fully resolved.

Bulgaria and Romania began planning the project more than 20 years before the 1989 fall of the Berlin Wall, which set the countries on a path to EU membership in 2007.

Germany paid for initial environmental studies that began 12 years ago, and the EU financed initial design work with a special fund to prepare ex-communist countries for EU membership.



Because the project lies on the priority Trans-European Network Corridor lV, from Berlin to southeastern Europe, it also qualified for EU support.

The EU, France and Germany are providing three-quarters of the bridge's current $290-million budget in grants and loans, while Bulgaria is paying the balance. With construction claims still under negotiation, the final cost has yet to be announced.

To procure the project, the Bulgarian government provided reference designs but allowed bidders to offer their own ideas. Major contractors from France and Germany also put in bids for the design-build contract, but FCC won it in January 2007.

Working with Madrid-based Carlos Fernandez Casado S.L., FCC “integrated the railway and the highway in the same bridge,” says Díaz de Argote. “In the tender documents, there were two bridges.”

The contractor also adopted a cable-supported, “extradosed” type of structure. With the pylons rising only some 21 m above the roadway, stay cables are set at shallow angle, providing some uplift but also acting as external prestressing for the deck girder.

FCC and its prestressing subcontractor, BBR PTE S.A., Madrid, also eliminated the conventional steelwork tower top. Instead, on either side of each pylon, cables are fixed to anchorages, which are tied together with prestressing.

Eliminating cable saddles will ease future inspection and maintenance, says High-Point Rendel's Jones.

FCC erected the main bridge using glued segmental match-cast deck-girder sections. The contractor cast over 450 deck pieces, each weighing up to 250 tonnes, near Vidim.

The deck has a roughly 7.3-m-wide x 4.5-m-deep box-girder spine with side walls up to 1.3 m thick. The girder's top slab extends outward to form the 31.5-m-wide deck. From either side of the girder's base, concrete struts rise at an angle to support the deck slab some 4.4 m from its outer edges.

Apart from the bureaucratic snags, the construction team had to deal with temperatures ranging from -20 to +40 degrees Celsius, says Jones. Crews also worked around an average of 100 large barges crossing through every week.

Seasonal variations in the water were a challenge when they exceeded eight meters, especially while boring the bridge's 2-m-dia, 80-m-long piles, notes Díaz de Argote.