Best of the Best Winners
www.enr.com/articles/60437-best-health-care-mayo-clinic-az-bold-forward-west-expansion
Mayo Clinic AZ Bold Forward West Expansion

The project team collaborated to ensure the hospital remained open to avoid disruptions to its patients’ experience.
Photo courtesy of Mayo Clinic

Best Health Care: Mayo Clinic AZ Bold Forward West Expansion

March 13, 2025

Mayo Clinic AZ Bold Forward West Expansion

Phoenix

Health Care

Region: ENR Southwest

Submitted by: DPR Construction

Contractor: DPR Construction

Owner: Mayo Clinic

Lead Design Firm: HKS

Structural Engineer: PK Associates

Civil Engineer: Kimley-Horn

MEP Engineer: WSP


The team working on the project to expand a top-rated Mayo Clinic facility in Phoenix performed extensive prefabrication work that allowed the hospital not only to avoid disruptions to patient care by remaining open during construction but also shaved months off the schedule.

The Mayo Clinic AZ Bold Forward West expansion included the addition of a 583,000-sq-ft, seven-story patient tower, a new emergency department that doubled the size of the existing one, and connection of the existing basement to the new one built 250 ft away.

The project team collaborated with the owner and other partners to be able to meet the goal of keeping the hospital open without sacrificing patient care during what could have been a disruptive project, according to its submission.

Mayo Clinic AZ Bold Forward West Expansion

Photo courtesy of Mayo Clinic

“Giving serious consideration to our patient-first mantra, we determined that it was possible to build the … building in one phase, after many initially thought it needed to be phased,” the team said.

Members worked with partners to build two 300-ft-long prefabricated, horizontal exit enclosed hallways to allow the public and hospital personnel to continue to access the emergency department. Materials that were prefabricated included headwalls, MEP racks and exterior panels.

Mayo Clinic AZ Bold Forward West Expansion

Photo courtesy of Mayo Clinic

This option allowed the main build to occur in one phase, shaving 17 months off the schedule, the submitters said.

Another challenge was connecting the existing basement to the new one. The construction team decided, after consulting with experts from the geotechnical engineer, trade partners and the owner, that the basements could be linked through tunneling, rather than by excavating the connection.

option saved more than a year off the original construction timeline and prevented major disruptions to the facility, the project team said. Members successfully tunneled 250 ft under the existing hospital to create a service corridor.