Submitted by The Engineering Co. The Rock Springs WWTP project installed $1.3 million worth of process equipment and constructed a new oxidation ditch to facilitate wastewater transfer, which assisted in the retrofit of existing facilities. Related Links: Intermountain Best of 2009 With its retrofit, Rock Springs WWTP implemented a state-of-the-art wastewater and solids reduction process called the Siemens Cannibal Solids Reduction process. Less than 20 plants in the United States employ this technique. Project Team: Rock Springs, Wyo., $13 million Owner: City of Rock Springs Contractor: Alder Construction Co. Design Firm: The Engineering Co. Start: Aug. 2005 Finish: June 2009
Submitted by Hughes General Contractors This project consisted of new construction of a 17,300-sq-ft events and training center for Lincoln County in Kemmerer, Wyo. The building was designed with enough flexibility to accommodate a variety of events such as exhibits, concerts, trade shows, conferences, business meetings and performing arts programs. Related Links: Intermountain Best of 2009 The building has four large rooms that can be opened, closed and combined in multiple ways to serve different functions. The facility can seat up to 650 for lectures or be divided into smaller training and conference rooms. A large roll-up door was provided
Submitted by Alder Construction Co. The South Valley Water Reclamation Facility’s Project 4C increased the facility’s average water flow from 38 million gal. per day to 48 million gal. per day, added structures to the campus and was completed while the current wastewater plant was online. Related Links: Intermountain Best of 2009 Project 4C consisted of many different complicated structures. The main structure houses a 6.6-million-gal., cast-in-place concrete aeration basin. Aside from the concrete work, a complicated array of mechanical components, such as sluice and slide gates, floating mixers, an electrical control room, splitter box with galvanized flumes and a
Submitted by Sahara Inc. This project consists of five new core-and-shell buildings for future retail and office tenant build-outs totaling 66,000 sq ft. The building materials are somewhat unique to Salt Lake Valley construction. The use of raw materials was common throughout the five buildings. Some of the materials are polished, clear-coated structural steel, unprimed structural steel, Corten corrugated panels installed flat in some areas and shingled in others. Photo: Sohm Photografx Related Links: Intermountain Best of 2009 Other materials include the use of acid-washed, galvanized roofing and wall panels and stainless-steel mesh for the entrance canopy. The project was
Submitted by Big-D Construction The Swaner Eco Center is a $4.6-million, 10,000-sq-ft, state-of-the-art facility that features exhibits, a contemporary theater, classrooms, space for private gatherings, a gift shop, an interactive climbing wall, a 400-ft pier, two decks and a four-story tower that overlooks the 1,200 acres of land owned and permanently protected by Swaner. Related Links: Intermountain Best of 2009 Known as the greenest building in Utah, the Swaner Eco Center was designed to achieve LEED-Platinum certification. The Swaner Eco Center achieved all 61 credits the project pursued. Key green building features include: a water reclamation system, photovoltaic solar panels,
Submitted by NWL Architects Emery County had struggled for many years maintaining an aging and antiquated indoor-pool facility. Both the pool and the building housing it had become serious liabilities for those who maintained and operated the facility. The final plans by the project team led to funding by the Community Impact Board. Related Links: Intermountain Best of 2009 The finished project consists of a six-lane, 25-yd indoor lap pool, and an outdoor family leisure pool with zero-depth entry, a big toy feature, a current channel and a large slide. Locker and toilet facilities accommodate both indoor and outdoor patrons.
Submitted by Geneva Rock Products Inc. This 10.2-mile highway project used the design-build process to accelerate the construction of a once-rural farm road that now carries 16,000 vehicles per day because of massive unanticipated growth in the area. Related Links: Intermountain Best of 2009 The major items of work included project design, acquisition of 220 right-of-way parcels, widening the existing road to two lanes in each direction, adding a center turn lane, bike lanes, two million sq ft of full-depth reclamation of the existing pavement, 55,000 ft of storm drain, 570,000 tons of imported aggregates, 220,000 tons of asphalt, three
Submitted by Ames Construction Inc. This project replaced two highway bridges using a technique called accelerated bridge construction, which utilizes precast concrete abutments and precast concrete deck panels. It also widened one mile of roadway and demolished an existing bridge. Related Links: Intermountain Best of 2009 This is the first bridge construction project in Utah to employ accelerated bridge construction. The two bridges were both built using precast concrete elements for the abutments, beam girders and deck panels. Because prefabrication of these elements could be accomplished in a controlled, offsite environment without jobsite limitations, constructability was improved, quality increased, costs
Submitted by Ames Construction Inc. The design-build of this 36-mile-long railroad spur included construction of five bridges. Under an aggressive schedule, crews moved 9.6 million cu yd of earthwork in nine months. The project included onsite processing of 382,000 cu yd of material for production of sub-ballast. Related Links: Intermountain Best of 2009 The bridges are all three-span structures utilizing precast concrete girders and cast-in-place footings, piers, abutments and decks. Three of the bridges provide crossings for county roads over the rail spur. The other two bridges provide crossing for the rail spur over the top of state highways. The