1
|
Corpus Christi Liquefaction Project Trains 1 & 2 Corpus Christi, Texas |
11,500
|
May 2015
2018 |
Cheniere Energy Inc. |
GC: Bechtel Oil, Gas and Chemicals Inc. |
2
|
Sasol Ethane Cracker and Derivatives Complex Westlake, La. |
8,900
|
March 2015
2018 |
Sasol North America
|
EPC: Fluor Technip Integrated Joint
Venture
|
3
|
Liquefaction Project Train 3 Freeport, Texas |
2,000
|
Oct. 2015
Dec. 2019 |
Freeport LNG
|
GC: Zachry Group
|
4
|
New Yuhuang Chemical Methanol Plant Vacherie, La. |
1,850
|
Sept. 2015
Q1 2018 |
Yuhuang Chemical Inc.
|
EPC: Amec Foster Wheeler
|
5
|
Breaking New Ground, Texas Medical Center
Renovation and Expansion Project Houston |
650
|
May 2015
2019 |
Memorial Hermann Health System
|
GC: Balfour Beatty
Design: WHR Architects |
6
|
183 South Austin, Texas |
581
|
Sept. 2015
2020 |
Central Texas Regional Mobility
Authority
|
GC: Colorado River Constructors, a JV of
Balfour Beatty Infrastructure and Fluor Corp.
Design: Parsons Brinckerhoff, AECOM |
7
|
Texas Children's Hospital Pediatric Tower
Expansion Houston |
506
|
Oct. 2015
June 2018 |
Texas Children's Hospital
|
GC: WS Bellows Construction Corp.
Design: FKP Architects; Walter P Moore;
Smith Seckman Reid Inc.
|
8
|
Daikin Hvac Equipment Engineering,
Manufacturing and Logistics Campus Waller, Texas |
417
|
March 2015
Mid-2016 |
Daikin Industries Ltd.
|
GC: D.E. Harvey Builders
|
9
|
300-MW South Plains II Wind Farm Floyd County, Texas |
390
|
Aug. 2015
2016 |
SunEdison LLC
|
GC: Mortenson Construction
|
10
|
Park West Student Housing College Station, Texas |
360
|
Sept. 2015
June 2017 |
Texas A&M University (Owner)
Servitas (Developer)
|
DB: The Weitz Co.
Design: PGAL |
11
|
Toyota's North American Headquarters Plano, Texas |
350
(est.)
|
Jan. 2015
2017 |
Toyota Motor North America Inc.
|
GC: Austin Commercial
Design: Corgan |
12
|
SH360 South Toll Road Tarrant County, Texas |
280
|
Aug. 2015
Feb. 2018 |
Texas Dept. of Transportation
|
GC: Joint Venture of The Lane
Construction Corp. and J.D. Abrams LP
|
13
|
Museum of Fine Arts, Houston Campus Expansion Houston |
225
|
Sept. 2015
Sept. 2019 |
The Museum of Fine Arts, Houston
|
GC: McCarthy Building Cos.
Design: Steven Holl Architects; Kendall Heaton Associates Inc. |
14
|
Stec Red Gate Reciprocating Engine Power Plant
Edinburg, Texas |
205 |
March 2015
June 2016 |
STEC (South Texas Electric
Cooperative)
|
GC: Red Gate Power Partners, a JV of Burns
& McDonnell and Casey Industrial Inc.
|
15
|
The Post Oak Mixed-Use Tower Houston |
200
|
April 2015
Fall 2017 |
Tilman J. Fertitta, Fertitta Entertainment
|
GC: Tellepsen Builders
Design: Gensler |
16
|
Christus Spohn Health System Master Facility Plan Corpus Christi, Texas |
189.5
|
Nov. 2015
Dec. 2018 |
Christus Spohn Health System
|
GC: McCarthy Building Cos.
Design: Perkins+Will |
17
|
Cypress-Fairbanks ISD High School #12 and
Elementary School #55 Houston |
165.2
|
Aug. 2015
July 2017 |
Cypress-Fairbanks Independent
School District
|
GC: Gilbane Building Co.
Design: Texas-IBI Group |
18
|
Interstate 10 Reconstruction “Go 10” El Paso, Texas |
158.6
|
158.6 Sept. 2015
Nov. 2018 |
Texas Dept. of Transportation
|
GC: Sundt Construction Inc.
|
19
|
US 290 Construction Engineering Inspection for
Sections A, B & C Houston |
150
|
Aug. 2015
Aug. 2017 |
Texas Dept. of Transportation
|
GC: Williams Brothers
CM: AECOM Technical Services Inc. |
20
|
I-49 North Bridge (Segment K) Phase 2 Shreveport, La. |
138
|
Jan. 2015
Sept. 2017 |
Louisiana Dept. of Transportation and
Development
|
GC: PCL Civil Constructors Inc.
|
21
|
Frost Tower Fort Worth |
125
|
Dec. 2015
Dec. 2017 |
Anthracite Realty Partners
|
GC: Balfour Beatty Construction
Design: Bennett Benner Partners |
22
|
Patrick Taylor Hall Baton Rouge, La. |
116
|
March 2015
Nov. 2017 |
State of Louisiana
|
GC: The Lemoine Co.
Design: Coleman Partners Architects LLC/ Perkins+Will, a Joint Venture |
23
|
El Paso Streetcar Project El Paso, Texas |
101
|
Oct. 2015
2018 |
City of El Paso (Owner)
Camino Real Regional Mobility
Authority (Developer)
|
CM: Atkins
Design: AECOM, with Alvidrez Architecture |
24
|
Hospitals of Providence Transmountain Campus El Paso, Texas |
100.3
|
March 2015
Oct. 2016 |
Tenet Healthcare Corp.
|
GC: Robins & Morton
Design: HKS |
25
|
Laredo 1 & 2 Ports of Entry Expansion Laredo, Texas |
100
|
Oct. 2015
Spring 2018 |
U.S. General Services Administration
|
GC: Brasfield & Gorrie
|