Top Starts project details were derived from data provided by Dodge Data & Analytics, reports from within the public record and information provided by the project teams.
Related Article:
Transportation, Mixed-Use, Tech Lead Top Starts in New York, New Jersey
Click below for earlier editions:
2018 | 2017 | 2016 | 2015
Rank |
Project/ Location |
Project Cost ($ Mil.) |
Start Date/ End Date |
Owner |
Team |
---|---|---|---|---|---|
1
|
HUNTERS POINT SOUTH, PHASE 2, PARCEL C (NORTH
TOWER) Long Island City, N.Y. |
500
|
Feb. 2019-
NA
|
TF Cornerstone |
GC: 52-03 Center GC LLC Design: ODA Architecture; SLCE Architects |
2
|
STATEWIDE CASHLESS TOLLING SYSTEM New York State |
355
|
Sept. 2019-Dec. 2020
|
NYS Thruway Authority
|
GC and Design: Cashless Tolling
Constructors LLC
|
3
|
BRIDGE WORK - PHYSICAL SECURITY/SAFETY
IMPROVEMENTS New York City |
264
|
Oct. 2019-
NA
|
US Army Corps of Engineers-NY
District (USACE)
|
GC: Kiewit Infrastructure Co.
|
4
|
COMMERCIAL DISTRIBUTION CENTER Bronx, N.Y. |
260
|
May 2019-
NA
|
Bruckner Boulevard Owner LLC
|
CM: Aurora Contractors Inc
Design: KSS Architects LLP |
5
|
GRASSE RIVER DREDGING Massena, N.Y. |
243
|
April 2019-Spring 2024
|
Alcoa Massena Operations
|
GC: Arconic Massena Operations
Dredging: J F Brennan Co. Design: U.S. Environmental Protection Agency-Region 2 |
6
|
RECONSTRUCTION OF TIMES SQUARE SHUTTLE, PHASE 3 New York City |
237
|
April 2019-March 2022
|
New York City Transit Authority
|
Design: WSP USA
GC: MLJ Contracting CM: AECOM |
7
|
BROOKLYN BRIDGE APPROACH, ARCHES, TOWERS,
RAMP SUBSTRUCTURES New York City |
236
|
June 2019-
NA
|
NYC Dept. of Transportation-Bureau of
Highways
|
GC: Navillus/MLJ Joint Venture
CM: Greenman Pedersen Inc. Designer: Parsons |
8
|
GREENPOINT LANDING MIXED-USE BUILDING AT 1 BELL SLIP Brooklyn |
200
|
Aug. 2019-
NA
|
Park Tower Group
|
GC: TG Nickel/Consigli & Associates LLC
Design: Handel Architects; Langan |
8
|
MIXED-USE BUILDING AT 2401 THIRD AVENUE Bronx, N.Y. |
200
|
April 2019-
NA
|
Brookfield Property Partners
|
GC: Hudson Meridian Construction Corp.
Design: Hill West Architects |
8
|
ZERO IRVING (UNION SQUARE TECH HUB) New York City |
200
|
Aug. 2019-
Dec. 2020
|
RAL Cos.
|
GC: Suffolk Construction
Design: Davis Brody Bond LLP; Vertex Engineering PC |
10
|
REGENERON MANUFACTURING FACILITY East Greenbush, N.Y. |
188
|
June 2019-
NA
|
Regeneron Pharmaceuticals Inc.
|
GC: BBL Construction Services LLC
Design: Jacobs Engineering Group; Hart Engineering |
11
|
OFFICE BUILDING (RENOVATION) ON PIER 57 New York City |
185.82
|
Sept. 2019-
NA
|
Super P57 LLC c/o RXR Realty
|
GC: Structure Tone LLC
Design: Robert Derector Associates; Diller Scofido + Renfro |
12
|
SECOND STREET TOWER, HACKENSACK UNIVERSITY
MEDICAL CENTER Hackensack, N.J. |
174
|
Aug. 2019-
2022
|
Hackensack Meridian Health
|
CM: W.M. Blanchard & Turner
Construction JV
Design: RSC Architects; EYP Architects; Langan |
13
|
ARCHER GREEN MIXED-USE DEVELOPMENT Jamaica, N.Y. |
170
|
Feb. 2019-
Feb. 2022
|
Omni New York LLC
|
GC: Lettire Construction Corp.
Design: Edelman Sultan Knox Wood Architects; Becker Engineering PC; Yu & Associates; DeSimone Consulting Engineers |
14
|
ONE PARK/VANTAGE MIXED-USE COMPLEX (LIBERTY
HARBOR NORTH)
Jersey City, N.J. |
160 |
April 2019-NA
|
Fisher Development Associates LLC
|
CM: AJD Construction Co.
Design: Perkins Eastman; Insite Engineering LLC |
15
|
GREENPOINT LANDING MIXED-USE BUILDING
AT 221 W. ST. Brooklyn |
150
|
Nov. 2019-
NA
|
Brookfield Property Partners
|
GC: New Line Structures Inc.
Design: Office For Metropolitan Architecture (OMA); Beyer Blinder Belle; Langan; DeSimone Consulting Engineers |
16
|
SILVER RUN ARTIFICIAL ISLAND TRANSMISSION
PROJECT Salem, N.J. |
146
|
May 2019-
June 2020
|
PJM Interconnection
|
GC: Silver Run Electric (Subsidiary of LS
Power)
Design: FirstEnergy Corp. |
17
|
HOLLAND TUNNEL LATENT SALT DAMAGE REPAIRS
AND MITIGATION New York City |
135.02
|
Oct. 2019-
NA
|
Port Authority of New York & New
Jersey Purchasing Services Division
|
GC: Tully Construction Co.
Design: Port Authority of New York & New Jersey Technical Center |
18
|
MIXED-USE DEVELOPMENT - TOWER B (PHASE 2) New Rochelle, N.Y. |
130
|
June 2019-
NA
|
RXR Realty
|
CM: Hudson Meridian Construction Corp.
Design: Paulus Sokolowski & Sartor LLC |
19
|
RIVERVALE SOUTH TO MARKET PIPELINE PROJECT New Jersey State |
127
|
Feb. 2019-
Sept. 2019
|
Williams Gas Pipeline Transco
|
Design: Williams Gas Pipeline Transco
|
Copyright ©2024. All Rights Reserved BNP Media.
Design, CMS, Hosting & Web Development :: ePublishing