This $27.5-million design-build renovation covered three basement floors in the nine-story Building 26 at the Naval Medical Center in San Diego.

Photo courtesy Stronghold Engineering
The fast-tracked project was designed to achieve LEED Gold certification.

The 193,729-sq-ft project included demolition; hazardous materials abatement; ADA-compliant restrooms; anti-terrorism measures; replacement of four large air-handling units; new ductwork; new electrical systems; erecting infection-control barriers during construction; and installing flexible, demountable partition panelized systems and sewer piping.

The team for the fast-tracked project, which was designed for LEED-Gold certification, maintained its schedule in an operational building while facing challenges in design, staging (on an adjacent 6,000-sq-ft tennis court) and phasing.

 

Key Players

Owner: U.S. Dept. of the Navy, San Diego

Contractor: Stronghold Engineering, Riverside

Lead Design: Ravatt Albrecht & Associates, Santa Maria

Submitted by Stronghold Engineering Inc.