The Nemours Foundation had a clear vision for its new children's hospital in Orlando: a world-class facility that would offer Central Florida a new level of pediatric specialty care, from minor injuries to the most complex of illnesses and conditions.
However, since Nemours had never built—nor operated—a full-service, in-patient pediatric hospital before, envisioning how to attain its goal was less clear. And from the beginning, complications would abound, starting with the fact that the new facility's location wasn't firmly set until the state of Florida authorized construction to begin in August 2009. Even then, only portions of the design had progressed to the point of being buildable. Other components would come into focus as Nemours brought the hospital's administrative and clinical leadership on board.
Despite these huge challenges, within 37 months, the Skanska USA-led design and construction team had birthed a $256-million, seven-story, 633,000-sq-ft hospital that was ready to serve. By overcoming so many unknowns while building a state-of-the-art health care facility—and for doing so with a stellar safety program and end results—ENR Southeast recognizes the Nemours Children's Hospital as its Project of the Year for 2013.
Impressive Achievement
ENR Southeast's judges were impressed with the Nemours project. Judge Howard Wertheimer, director of capital planning and space management at the Georgia Institute of Technology, Atlanta, called it a "very well-crafted facility with finely detailed and executed results."
The completed hospital's 400,000-sq-ft in-patient portion includes 95 private patient rooms; an operating-rooms suite; full radiology and nuclear medicine capabilities; and a pharmacy. The 200,000-sq-ft clinic includes 85 exam rooms, plus an education center with conference facilities and a 225-seat auditorium.
While some of the logistical hurdles could have been smoothed out over time, Nemours officials say the urgency to build wouldn't allow for that time.
"Greenfield projects such as these don't happen often and inherently have their own construction issues," says Nelson Roque, Nemours' director of planning and construction. "But we just couldn't afford to wait for everything to fall into place before getting started."
In fact, Nemours wanted to get started before it even had assigned staff to make key project decisions.
"We could get going on the core infrastructure, but things like the operating rooms, radiology labs and food service had to be deferred until Nemours could get clinical staff on board to make decisions," says Andy Allen, Skanska USA's project director.
The prospect of having design continually play catch-up with construction would test the patience of the project team. But for the most part, collaboration, rather than contention, won the day.
"Skanska went to great lengths to build relations with the design team, which was important with the changes coming in so fast," says Veronique Pryor, project manager for designer Stanley Beaman and Sears.
One certainty from the outset was the need to have the hospital's landscaping—which would ultimately include two therapeutic roof gardens—as well-established as possible by opening day to achieve the "Hospital in a Garden" design theme, which emphasizes nature's role in the healing process. That meant that landscaping was installed at the start of construction.
This was no small point, and caught the eye of ENR Southeast's judges. Georgia Tech's Wertheimer called it "a very forward-thinking and innovative approach."