Cost Critique Coming For Orlando's Delayed Performance Venue
Image: Courtesy of Dr. Phillips Performing Arts Center

PCL Construction Services, the pending owner's representative for the $383-million Orlando Performing Arts Center, is reviewing Balfour Beatty's construction management contract and subcontractor bids in an effort to cut costs. The first phase of the venue designed by Barton Myers Associates is estimated at $202 million, or $17 million more than is available. The PCL report is due May 9.