...resulting increased water flow capacity below the road cuts the frequency of total tunnel closures, he adds.
Organizing
In winning the contract, SMART JV secured the overall task of designing, financing and procuring the entire project and operating the highway portion. The government will manage its flood control functions. But the joint ventures equal partners, Malaysia Mining Corp. (MMC) Berhad and Gamuda Berhad, lacked the technical experience for such a project, says Sivalingam. With annual sales of about $400 million, Gamuda, for example, has built drill-and-blast tunnels, but this is its first machine-driven project.
For construction, MMC and Gamuda set up a separate joint venture (MMCG) and awarded it a turnkey contract in 2002. When Gus Klados came in June 2002 as senior tunnel specialist, the design was partly done but the tunneling method was undecided, he says.
KLADOS |
By then, Mott MacDonald already had recommended using slurry-faced TBMs, but vendors also had proposed earth-pressure-balance technology. Having struggled in a previous Singapore job with an earth-pressure TBM in difficult rock with high water pressure, "I brought confirmation that we needed a slurry shield," says Klados.
Klados also brought enough experience and contacts to create a tunneling organization almost from nothing. He started in the business at home, on the Budapest metro in the early 1970s. From there he moved to the Calcutta subway job, before joining the Channel Tunnel team in England. He then took in the Lesotho highlands water project and the Athens metro before heading for a decade in East Asia.
"I had to set up a company within the joint venture but I didnt have experienced people," says Klados. "Gamuda had done the best it could in the circumstances.... They [let] me do the job. It was [for them] a big leap of faith."
For essential "back office engineering and work preparation," Klados relied on Paris-based Vinci Group. Former colleagues helped to specify and procure the segment molds in France and the TBMs in Germany. Altogether, he recruited 13 expatriate tunnel specialists.
The team built up by Klados wins plaudits from Peter Chiappa, project manager with Germanys Wayss & Freytag Ingenieurbau A.G., Frankfurt, which now is driving the tunnels north 5.3 km. "I was very surprised from the very beginning how professionally they handled this," he says. W&F in early 2003 won the contract to drive the northern tunnel section, with an option for the southern 4 km that never materialized.
"We had to decide whether to outsource the whole thing or do one half ourselves," explains Sivalingam. Without any bored tunnel experience, the Maaysians took on the southern drive aiming "to become a serious tunneling company," he adds. As a result, Klados took direct control of the southern drive, while overseeing all tunnel work.
Double Deck. Highway decks are attached to lining segments with shear connectors. |
Early Changes
MMCG first chose to procure tunneling equipment for the north drive and hand it to a contractor, when appointed, to save time. Because of its limited TBM experience, the team decided to buy the TBMs with all associated equipment from a single supplier. But W&F had other ideas.
"As discussion went on, the whole concept changed," says Chiappa. Apart from having its own bentonite separation plant, "we offered a TBM with second hand components, which had a much shorter delivery time," he adds. The move saved the contractor several million dollars and got the machine on site three months ahead of the unit destined for MMCJVs south drive, he says.
Germanys Herrenknecht A.G, Schwanau, won orders for both machines in 2003. The 13.2-m-dia mixshield TBMs use compressed air to balance ground pressure in the face. Bentonite is pumped through a pressure wall and then via a compressed air chamber, which ensures the slurry pressure matches that in the soil and water ahead.
The advantage of this arrangement over conventional slurry machines is "if you come out of rock and hit an area of soft ground, the compressed air expands [quickly] and the slurry flows in to fill the partial void. You can maintain pressure to support the face," says Darby.
The feature seems well suited to Kuala Lumpurs tricky ground. Under superficial loose alluvium, the tunnel route cuts through complicated limestone with a variable profile and containing dissolved cavities filled with peat-like soil. Most of the south drive and over half the north bore is in this karstic rock, while the rest is in soft material.
Tunnelers know when they hit a cavity because cutting resistance drops, slurry changes color and the volume of grout needed behind the segments doubles or triples. "We have to watch it like an eagle," Klados says. Solution caverns can be warren-like, consuming huge amounts of bentonite.
With about 13 m of cover in places, "it is a very shallow drive, especially in areas in the south drive where we are driving in soft rock...the bottom part of the face might be in limestone with alluvium at the top," says Klados. With such treacherous conditions, the contractor has not stinted with soil investigations.
Curves. Tunnel has tighter bends than normal for a large TBM. |
TBM Track
Both TBMs cutterheads are mounted on a spherical main bearing to steer a 250-m radius, says Klados. Because the tunnel follows roads as much as possible, its bends are much tighter than would be normal for such a large machine, he adds.
The first machine, W&Fs, arrived in Kuala Lumpur a month after the 150-m-long, 25-m-deep launch pit was completed in January of last year. The second machine followed a few months later.
W&Fs machine set off on its 5.3-km drive last May, with Chiappas team "fine tuning" all the processes to the difficult ground, he says. Chiappa knows of no other bentonite machine to have worked in such karstic rock. Having built up a rhythm of work, W&F was interrupted after some 700 m by the huge open pit of the north highway ramp.
Having hauled the machine some 200 m through the pit, W&F restarted work in February, aiming to finish by May 2006. The average advance in the first 700 m was just over 5 m in 24 hours, exceeding that by 50% toward the end, says Chiappa. He hopes to do better than 10 m a day once his team regains its beat.
MMCGs southern TBM, took off last August, for completion in March 2006. Working around the clock, the TBM has achieved 100 m in a week, a "good performance with such a large diameter slurry shield," says Klados. In following the W&F machine by a few months, MMCG will have gained vicariously, believes Chiappa. "When mistakes were made, they didnt need to repeat them," he says.