Corps Rebids Protested Flood Control Project, With Changes
Following bid protests by losers of a $675-million flood control project in New Orleans that were upheld by the U.S. Government Accountability Office, the Army Corps of Engineers is seeking new bids from the contract’s original five short-listed teams. Some observers termed the move to re-procure the project as highly unusual and bidders are not saying how they will proceed.
The move to re-bid will now push contract award for the Permanent Canal Closures and Pump stations (PCCP) to April 2012 and final project completion to October 2015, almost a year later than originally anticipated.
The design-build contract was awarded in April to CBY, a joint venture of CDM, Cambridge, Mass.; Birmingham, Ala.-based Brasfield & Gorrie; and Yates Construction, Philadelphia, Miss.,
Two competing bidders then protested the award: Ft. Worth-based PCCP Constructors, comprising Kiewit Corp., Omaha, Traylor Bros., Evansville, Ind., and M.R. Pittman Group, New Orleans; and Bechtel Infrastructure Corp., Frederick, Md.
GAO upheld the protest Aug. 4, noting the conflict of interest possibility, faulting the Corps’ evaluation of technical proposals and asserting that the agency may have misled bidders about the role of price in the evaluation.
However, after its own investigation sought by GAO, the Corps has found no organizational conflict of interest by Richmond Kendrick, former chief of program execution for the Corps Hurricane Protection Office in New Orleans.
Kendrick was hired in September 2010 by CDM, which headed the original winning project team, less than a month after he retired from the Corps office.
Col. Ed Fleming, commander of the Corps New Orleans district, says he is confident that re-bidding the contract is the best approach for a “path forward that is in compliance with the GAO's recommendations and will result in the expedient construction of the three outfall canal permanent closures and pumps."
However, it is "almost unprecedented" for the selection to be thrown out, says Rob Vining, national water resources practice leader at HNTB Corp. and former Corps chief of civil works program management. “When I worked for the Corps, if there were issues raised, the GAO would recommend putting internal controls in the process, but they would not throw out the whole selection,” he says.
The decision also indicates that the district concluded it would be too complicated to proceed with a best value selection, so it changed the [request for proposals] to be price-based, according to Vining. “In my mind, the Corps changed the type of procurement it will be this time,” he says. “The Corps lost a year on the selection process, and that’s a year those pumps could have been in place.”
If the details can be worked out, it may be possible to have at least some of the bidders start work immediately. However only that bidder whose actual performance on the job was best i...
The way a "best performing" contractor award might work is to award 2/3 of the contract to 3 contractors with the final 1/3 of the contract awarded to that contractor who has done the ...
thats stupid and not woth pointing out the slew of other problems and fingerpointing that would ultimately occur 2/3 of the way thru the project not to mention how to deal with faulty c...
Constructive criticism of what I term "the best performing contractor" contract are welcomed. The objector fails to note that it is in no contractor's interest to make trouble on the jo...
The objector notes correctly that the "best performing contractor" type of contract does not guarantee that the final portion of the job will be performed satisfactorily since there are no longer checks on his performance by the losing contractor. Naturally there are still checks on contractor performance as their would be with a single contractor and of course the problems confronting engineers dealing with badly performing "low bid" contracts are very greatly diminished. The objector should look for Utopian contracts in Utopia.
What I have proposed originated in the mind of a very great physicist,Robert R. Wilson who built Fermilab ahead of schedule and under budget using this firm of contract; and who was known for his ability to bring in projects ahead of schedule and under budget.Although officially he was classified as a physicist, I would classify him as a very great engineer too for his great ability to bring in complicated projects ahead of schedule and under budget.