PROJECT COST: $47.1 Million
This new five-story concrete structure is designed to consolidate a number of city administration offices and service departments that interact with the public. A three-story parking garage provides space for 360 cars. Site improvements include a water fountain, waterfalls, exposed aggregate concrete and brick pavers.
Started: April 2009
Target Completion: October 2010
Owner: City of Chandler
Design Firm: SmithGroup, Inc.
General Contractor: Sundt Construction, Inc.
Construction Manager: Abacus Project Management, Inc.
Engineers: Dibble Engineering; Caruso Turley Scott; SmithGroup
Landscape: GBtwo Landscape Architecture
Subcontractors: Kearney Electric; Premier Mechanical; Aero Automatic Sprinkler; KT Fabrication; Sundt Concrete; Castle Steel; Pete King Corp.; Century Roofing