Submitted by Hunt Construction Group
Located in the heart of downtown Phoenix, phase one includes a five-story underground parking garage, a 28-story office tower, retail and off-site utilities.
The 65-ft-deep excavation and complex utility relocation occurred below one of the oldest portions of the Central Phoenix travel corridor.
Hunt debuted a new modeling software that embeds 6D information electronically, including as-built drawings, maintenance manuals, commissioning FM data and service schedules—all in one place.
To allow more column-free space on each floor, the designers created a floorplate with columns pushed to the perimeter of the building. The team also notched the corners, adding more corner offices as well as creating a unique look to the building exterior. A custom formwork system allowed crews to maintain an aggressive one-floor-a-week schedule.
Developer/Owner: Red CityScape Development, LLC.
General Contractor: Hunt Construction Group<
Architect: Callison
Engineers: David Evans and Associates; PK Associates; GluMac
Landscape: Murase; Floor Associates
Subcontractors: Beusing Corp.; Suntec Concrete; JEN Electric; HACI; W.J. Maloney Plumbing; Walters and Wolf; Aero Automatic Sprinkler Co.; Able Steel; Sun Valley Masonry; Arok; ISEC; ColorCor Painting; Dakota Sealants