Marco Island Marriott Renovation
Marco Island, Fla.
Award of Merit
Owner Massachusetts Mutual Life Insurance Co.
Lead Design Firm EOA Architects
General Contractor PCL Construction Services Inc.
The Marco Island Marriott was shut down to accommodate this fast-track, 90-day project that included the redevelopment of the resort’s lobby, porte cochere, grand entrance, two restaurants and main kitchen. The $25-million project encompassed 62,000 sq ft of renovated space, completed in 78 working days, equating to more than $300,000 of work installed per day. Over the course of the project, an average of eight RFIs were written and solved each day. Working with all teams co-located on site allowed the team to solve challenges as they occurred without delays to the project schedule.