St. Anthony Shawnee Hospital Expansion
Shawnee, Okla.               
Award of Merit

Owner: SSM Healthcare of Oklahoma
Lead Design Firm: HGA Architects & Engineers
General Contractor: Turner Construction Co.
Civil Engineer: Smith Roberts Baldischwiler LLC
Structural/MEP Engineer: HGA Architects & Engineers
Subcontractors: Irwin Steel; LASCO; Lithko Contracting Inc.; Matherly Mechanical; Oklahoma Electrical Supply Co.; TEPCO; Bentley Flooring


A building was demolished to make way for the three-story, 115,000-sq-ft addition between the existing Shawnee Hospital and a clinic. The $45.88-million project also included a 15,000-sq-ft renovation and asbestos abatement on the hospital. Noise, dust control and cleanliness were critical for environmental quality on the medical campus.

Unforeseen underground utilities had to be relocated before construction, requiring a detailed schedule for the installation of new materials. The active hospital campus called for especially close communication to organize the site into efficient work areas and ensure minimal disruptions. The project was completed on time and budget in May 2016.