Pittsburgh's Liberty Bridge Almost Finished

Pittsburgh’s Liberty Bridge will be fully completed in the new year.
PHOTOS COURTESY OF THE PENNSYLVANIA DEPT. OF TRANSPORTATION
Pittsburgh’s Liberty Bridge will be fully completed in the new year. A 2016 fire hampered the three-year project by closing the bridge for 24 days. The project team is working on punch-list items and will also replace a pedestrian railing damaged by a driver in August. The Pennsylvania Dept. of Transportation says it will seek reimbursement for the $30,000 railing from the driver.
After substantial construction was completed in July, the $81.8-million project’s full completion date was delayed to Aug. 26 due to unforeseen steel work and added sidewalk work. End-stage tasks include pressure washing and repointing decorative sandstone, touching up paint, asphalt sealing and removing form work, which should now be completed in January, PennDOT says.