Planning
Alabama Navistar Big Bore Diesels LLC is planning to expand its plant in Huntsville. The expansion includes the relocation of a gear box assembly line to the Huntsville plant and the construction of a new 110,000-sq-ft east wing. The project is valued at $125 million. Navistar Big Bore Diesels LLC, Attn: Marty Ketelaar, 485 Short Pike Road SW, Huntsville, 35824. DR#20-00478434.
Alaska Lynxs Group is planning to expand the UPS Cargo Operations Building at Anchorage International Airport by 190,000 sq ft. The project is valued at $110 million. Lynxs Group, Attn: Raymond Brimble, 3501 Manor Road, Austin, Texas 78723. DR#20-00686250.
Colorado Cypress Creek Renewables is planning to build Sundance Solar, a 75-MW solar power plant, at the intersection of Kiowa-Bennett Road and State Route 154. The project is valued at $136 million. Cypress Creek Renewables, 3402 Pico Blvd., Santa Monica, Calif. 90405. DR#20-00669049.
Iowa Echo Development, Brent Dahlstrom and ISG Engineering are planning to develop a residential subdivision on 177 acres in southwest Cedar Falls east of Union Road and north of West 27th Street. Approximately 500 single-family homes are to be built on various lot sizes, along with roads and other neighborhood infrastructure. The work will be divided into seven phases. The project is valued at $88.9 million. ISG, 314 East Fourth St., Waterloo, 50703. DR#19-00797168.
Nevada The city of Henderson plans to build the West Henderson Recreation and Aquatic Complex. The 62,500-sq-ft facility will have multiple meeting rooms, a gymnasium and athletic facilities. The project is valued at $97.5 million. City of Henderson, Attn: Scott Majewski, 240 S. Water St., Henderson, 89015. DR#15-00641928.
North Dakota The Theodore Roosevelt Center is planning to construct the Theodore Roosevelt Presidential Library in Medora. The library archive will be mostly electronic, since the physical Roosevelt papers have long since been deposited with institutions like the Library of Congress. The museum will explore Roosevelt’s life using physical objects, framed documents, films, touch-screen kiosks, timelines and more. The library will also host events, lectures, symposia, seminars, teacher institutes and other public activities. Three firms, Snøhetta, Studio Gang and Henning Larsen, have been selected as finalists to design it. The project is valued at between $125 million and $150 million. Theodore Roosevelt Center, 291 Campus Drive, Dickinson, 58601. DR#13-00513364.
Ohio Willis Creek Capital Management is planning to develop the Bluegrass Park Apartments, a mixed-use project in Grove City. The project will entail between 10 and 30 buildings with about 387,000 sq ft of space, with medical office space and retail space of about 5,000 sq ft, a day care center and either 384 multi-family units including 120 of senior housing or 264 units including 64 townhomes. The project is valued at $64 million. Willis Creek Capital Management, Attn: James Schrim III, 580 N. Fourth St., Columbus, 43215. DR#19-00768127.
Bids, Contracts, Proposals
Maryland-Delaware The U.S. Army Corps of Engineers has awarded an $8.8-million firm-fixed-price contract for maintenance dredging of the Inland Waterway Chesapeake & Delaware Canal to Great Lakes Dredge & Dock Co. LLC. Pearce Creek DMCF and Reedy Point South will be used for placement of material. This is a contour dredging project. The environmental dredging window for this project is between Oct. 1, 2020, and March 31, 2021. Great Lakes Dredge & Dock Co. LLC., 2122 York Road, Oak Brook, Ill. 60523. DR#20-00596737.
Oklahoma Merak Group LLC has started constructing the Muncie Power Products manufacturing facility in Tulsa. The 250,000-sq-ft building is located at 1555 E. Mohawk Blvd. The project is valued at $50 million. Construction is expected to be completed by April 2021. Merak Group LLC, 809 E. Jackson Place, Broken Arrow, 74012. DR#19-00568142.
Bid, Proposal Dates
Connecticut 9/1 The U.S. Dept. of Veterans Affairs is seeking bidders to renovate and expand its primary care clinic in Newington. The work includes renovating 20,000 sq ft of Building 2C and Building 2W and building a new 5,000-sq-ft structure on the courtyard adjacent to Building 2W. In addition, it involves renovating a 7,107-sq-ft space in the lower level of Building 2E and a 1,876-sq-ft storage space on the fourth floor of Building 1. The project has been designed by Toland Mizell Architects Inc. The project is valued at between $5 million and $10 million. U.S. Dept. of Veterans Affairs, Attn: Gregory B. Parker Jr., 6150 Oak Tree Blvd., Independence, Ohio 44131. DR#19-00724465.
North Carolina 9/10 North Carolina State University is requesting statements of qualifications from architectural/engineering firms interested in designing an integrative sciences building for its campus in Raleigh. The 145,000-sq-ft building will include classrooms, teaching labs, research labs, research core facilities, collaboration/study space and office space. It will focus on chemistry, biochemistry and biotechnology. The project is valued at $160 million. North Carolina State University, 2701 Sullivan Drive, Raleigh, 27695. DR#20-00691698.
Much information for Pulse is derived from Dodge Data & Analytics, the premier project information source in the construction industry. For more information on a project that has a Dodge Report (DR) number or for general information on Dodge products and services, call 1-800-393-6343 or visit the website at www.dodgeleadcenter.com.