Schuyler Heim Bridge Fender Lowering
Long Beach, California
BEST PROJECT
KEY PLAYERS
OWNER: California Dept. of Transportation
LEAD DESIGN FIRM | CIVIL ENGINEER: Schwager Davis Inc.
GENERAL CONTRACTOR: MCM Construction
As part of the replacement of a critical bridge serving the ports of Los Angeles and Long Beach, the project team developed a strategy to install two 2.1-million-lb precast concrete bridge fenders to safeguard the structure from vessel impacts. The original plan to use cofferdams for the project posed a host of cost, schedule and operational risks because extremely large structures would be required to accommodate the 132-ft by 18-ft by 20-ft fenders and provide sufficient working room. Installing the fenders in segments would still require building sizable cofferdams and add time to the construction schedule.
Related link: ENR California Best Projects 2021
(Subscription Required)
Rather than trying to work from below the waterline, the project team elected to use a more cost-effective approach based on post-tensioning methods and materials. The fenders would be fabricated using cast-in-place concrete near their final installation point and lowered into the water using bars and rams typically employed in post-tensioning. Divers then installed formwork to grout-fill the annular space between the piers and the fenders.
In order to lower the huge fenders evenly, eight center-hole hydraulic jacks were plumbed in groups to form a three-point support system. Spatial constraints imposed by the bridge soffit above the fender location necessitated a custom design of bar couplers and components.
Prior to mobilization, the specialty subcontractor completed full-scale proof testing of all lowering components and equipment to ensure proper functioning of the lowering system.