INTERMOUNTAIN HEALTH SUPPLY CHAIN FULFILLMENT CENTER & ACUTE CARE PHARMACY EXPANSION

Midvale, Utah

BEST PROJECT

Submitted by: Jacobsen Construction

OWNER Intermountain Health

LEAD DESIGN FIRM VCBO Architecture

GENERAL CONTRACTOR Jacobsen Construction

CIVIL ENGINEER Great Basin Engineering

STRUCTURAL ENGINEER Reaveley Engineers

MEP ENGINEER VBFA

ELECTRICAL ENGINEER Spectrum Engineers


To strengthen the delivery logistics required to efficiently service 24 hospitals and 160 clinics across the Intermountain West, this $16-million expansion brings an additional 46,000 sq ft to this fulfillment center and pharmacy. A new space houses medical supplies and an improved pharmacy equipped to quickly provide help to patients systemwide who require life-saving medications.

Scope of work included modifications to utilities, reconfiguration and expansion of parking spaces and new landscaping.

Intermountain Health Supply Chain Fulfillment Center

Photo courtesy Jacobsen Construction

This tilt-up concrete structure was built on an EPA-designated reformed Superfund site. Smelting plants processed lead and other heavy metals until 1958, which contaminated soil and groundwater in the area. Although remediation efforts have been ongoing for decades, each new project on the site still faces hurdles in protecting against toxic conditions. A geotechnical examination of the soil found hazardous toxins present, so the team put precautions in place to protect the construction crews and the building’s end users. These steps included using protective fabric liner in excavated areas, particularly where personnel worked in utility trenches replacing removed soil with flowable fill when backfilling plumbing lines and other utilities. Handwashing stations were installed immediately adjacent to high-hazard areas. Working closely with multiple environmental regulatory authorities, crews performed daily inspections of soil conditions. At a cost of $100-plus per cu yd, all contaminated soil excavated was disposed of at an EPA-approved site.

Delivery of a critically important air handling unit was pushed back nearly six months due to both a slow supply chain and a slight unit modification requested by the owner that unexpectedly reset the project’s place in line. This unit is responsible for preserving consistent temperature conditions throughout the warehouse, an absolute requirement for making the space fully capable of housing sensitive medical supplies and equipment. To overcome this timing change, the contractor worked closely with key subcontractors to resequence several scopes of work, which ultimately delivered the project on time and under budget.