Image in modal.
Q4 Tech Focus

In 2003, Stephen Kieran and James Timberlake wrote Refabricating Architecture, a book that argued the time had come to reevaluate and update the basic design and construction methods that have constrained construction and kept it closer to agriculture in terms of efficiency rather than manufacturing industries such as automotive production and shipbuilding.

The principals of the eponymous Philadelphia-based architecture firm KieranTimberlake further argued that it’s process engineering that allowed the automotive, shipbuilding and aerospace industries to work faster than previous cost and time constraints had allowed and redefine their scopes of work—allowing improvement in quality and scope that transcended the traditional limits of those cost-time resources.

Parametric building information modeling was touted as a catalyst for enabling a transition to industrialized construction, as it had for automotive manufacturing. But the last two decades have seen only moderate change in construction processes, as change orders and requests for information have become enshrined in cloud-based project management platforms and BIM authoring software.

While manufacturing tolerances are generally tighter and more precise due to computer-controlled machinery and processes in fabrication shops and factories, construction tolerances have stubbornly remained wider and more varied in order to accommodate the variability of on-site conditions. In short, 3D design has not yet brought on a wide shift to tighter tolerances or enabled higher cost certainty from offsite fabrication, outside of assemblies produced by electrical and mechanical contractors.

There are bright spots, however. Design firm WSP and contractor Mace Group are pursuing a new approach that may mark a shift in the quest to industrialize construction processes.

man doing 3d modeling on a computer

WSP’s plans for Manchester Airport’s nodes began as a 3D Revit model.
Photo courtesy of WSP

Rethinking Assembly

Manchester Airport model

WSP’s plans for Manchester Airport’s nodes began as a 3D Revit model, with a kit of just 67 parts, first shown in a scale model at Autodesk University.
3d model courtesy of WSP

WSP has developed a kit-of-parts approach as a program-level design management process that combines customized offsite manufacturing and a design for manufacturing and assembly (DfMA) workflow. Autodesk is partnering with WSP on the initiative, with Az Jasat, Autodesk senior manager for industrialized construction, assisting with technology implementation. The process lets design teams balance out the use of different construction methods, breaking down building designs into larger components that can be manufactured offsite at more precise tolerances before being transported to the site for rapid assembly.

By tracking these components, WSP can scale up from a per-project level and set program-level policies that align to a client’s specific goals. One current WSP client is Manchester Airport in Manchester, U.K. The country’s third-largest airport is adding a concourse with 12 gates that will allow the world’s biggest passenger planes, Airbus A380s, to pass side by side as they move around Terminal 2. The new concourse is the largest part of a $1.65-billion expansion.


ENR Construction Cost Data Dashboard
GET STARTED

The kit-of-parts approach promoted by WSP and the project’s construction manager, Mace, involves installing 150 precast concrete pilings for foundations to support the concourse and a number of steel structures called nodes, which allow different-sized planes to be connected to it via air bridges. Each node is comprised of a stairway and elevator core building that allows passengers to change levels between the plane and the gate via a fixed link to the terminal.

Traditionally, the nodes would be constructed in the field from thousands of components and transported individually to site. However, the kit-of-parts approach has reduced the number of parts to just 67, which are all able to be transported to the site via flatbed trucks.

“You’ve really got to design the details to suit the [construction] sequencing,” says Dale Sinclair, head of digital innovation at WSP. “That’s probably been our main learning point, how to get much slicker at sequencing and the whole lifting [via crane] piece of the installation.”

detailed drawings

WSP’s plans for Manchester Airport’s nodes began as a 3D Revit model, with a kit of just 67 parts, first shown in a scale model at Autodesk University, and on to detailed drawings for onsite construction.
3d model courtesy of WSP

Sinclair says that in collaboration with Mace, WSP invented a bracket to connect the concrete substructure interfaces to the rest of the node’s core and facade. That key first step allowed the construction team to take advantage of the much tighter manufacturing tolerances and broader economies of scale that come with reducing the node to so few components.

“The brackets all get ‘lasered in,’” he adds, referencing their placement with laser positioning systems. “The point is that you’ve got a relatively small thing that you can position with the laser before you bring in the really big things. [It lets you make] sure that the site’s essentially ready for the tolerances of the bigger things.”

Sinclair’s team at WSP had gotten used to working this way and brought Mace into meetings early on in the design process. But some new engineers were brought in as the scope of the project grew, and getting them used to detailing connections, designing temporary falsework and other fine details took some educating. WSP also worked closely with the project’s specialty steel engineer, Pro Steel, to ensure the nodes came together as planned. WSP is currently working on a program for the U.K. Environment Agency delivering environmental monitoring stations across the countryside that will be built from the kit-of-parts approach.

airport node
airport node

Each airport node was assembled by completing the stairs and elevator core first for stiffness. Steel struts and cladding are then connected to these core components.
Photos courtesy of WSP and Mace

It All Fits Together

Before working with WSP on the Manchester Airport nodes project, Mace had already used volumetric and modular techniques to deliver a bridge over a taxiway at Manchester Airport and a new air traffic control tower at London’s Heathrow Airport. In those cases, the contractor used strand jacks to slide in bridge sections and an onsite manufacturing facility to fabricate parts of the tower. These approaches allowed the airports to remain in operation during construction, with fewer disruptions to normal activities.

“Dale and I looked at this from that start, and we, at Mace, invested a significant amount of research and development to have the intellectual property, but we needed Dale’s expertise to turn that into an Autodesk model,” says Matt Randall, director at Mace.

Using the WSP kit-of-parts approach, Mace was able to reduce its crane demands down to six lifts a day and get the schedule down to a three-week build time.

“If you compare that to a traditional build, that’s 110 days. So if you’re closing a stand for 110 days, they’re taking one-hundred-grand revenue a day off the stand. And then you can do that [same work] in around 12 days, suddenly it makes a lot of sense,” he says.

Mace estimates that the kit-of-parts approach—along with a temporary entrance that can bypass the traffic in and around the airport due to the reduced volume of deliveries—has taken 83,000 worker-hours off the project schedule and is saving about 125 tons of CO₂ that would have been emitted waiting on a more traditional delivery schedule and sequencing.

The parts for each node are split up into spine walls, corridors, roof cassettes, stairs, stair landings, trestles and fixed-link bridges. The diversified supply chain of where these items are fabricated is itself a virtual tour of the U.K., Randall notes.

“You’ve got some in Wales, some in Manchester, some in London. And these are where the build is being done; it’s being done miles away from the airport,” he explains. “But everybody is building standardized sub assemblies. And by diversifying the supply chain, you can then really increase your productivity.”

The finish and paint shops for the sub assemblies are also in the U.K., and if production bottlenecks become an issue they can share the load to get things done.

Like all construction projects, there were some unknown factors. Randall says one area Mace is looking to improve is the foundation work. The contractor created footings to get the site to a fixed grade level so that all the sub assemblies can work off the same reference altitude, but that took time and effort. “The groundwork has taken such a long time to get these bases into alignment,” he says. “That’s something that we’ve looked at improving to try and simplify the foundations.”

four completed nodes
four completed nodes

An average of six workers was used to construct the four completed nodes at Manchester Airport. The final four nodes are on track to be completed by January 2025.
Photos courtesy of WSP and Mace

From Design to Real Steel

Pro Steel is managing the steel-to-steel connection design, steelwork manufacturing, intumescent fire-rated paint system application, off-site steelwork preassembly and the cladding and site installation of all structural steelwork for Manchester Airport’s fixed-link bridges and node buildings.

“We’ve built four of the eight nodes so far, and every single one of them is getting quicker,” says Steve Richardson, project manager for Pro Steel. “The target for a single node is basically three weeks, and we’re starting to knock on the door of that. The target for a double node is six weeks. And the next double node that we put up, and very much expecting that, and that’s a fully clad node, in six weeks.”

Interior finish building trades move in and fit the nodes out after installation, but work on them is more or less finished after a three- or six-week construction schedule. Richardson says the nodes are averaging six workers apiece. He says Pro Steel briefs its workers using the 3D models to show context, orientation and constructability issues before they get started, “because it’s much easier to look at a 3D image.”

One hiccup when going from design to construction on the nodes was that some connections designed in the model needed to be changed for constructability.

“A typical double node has five panels on each side, plus a corner panel,” Richardson says. “She’s 15 meters tall. Each panel is 3 meters wide, approximately. In terms of slotted holes, they had slotted holes on the vertical faces where they connect to each other, which was largely completely pointless because they share a foundation. Yet, on other elements, where you’ve got three separate large components being joined together … there were no slotted holes. One of the things I’ve done since I came here was look at the design, go back to WSP and say, ‘You need to give me slotted holes in these particular brackets.’”

WSP’s Sinclair adds that his team learned a lot about construction sequencing for crane picks and have since incorporated their lift strategies into the design for the U.K. Environmental Agency stations.

Exchange’s framing

The 3D model of Exchange’s framing also acts as a roadmap to its finished installation.
Photo and image courtesy Liftbuild

DfMA in the USA

A U.S.-based project that used a similar kit-of-parts approach is the Exchange condominium tower in Detroit (ENR 10/31/22, p.18). Assembled by LIFTbuild, a top-down construction subsidiary of Barton Malow Corp., that project was delivered via a series of strand jacks and a proprietary “tray” to lift and bolt floor slabs into place after building them on the ground to reduce safety risks and accommodate a tight site with no laydown room. LIFTbuild used supply chain and DfMA tactics similar to the ones WSP, Mace and Pro Steel have used on the Manchester Airport nodes.

“A lot of what we did was taking advantage of assembling things at grade,” says Joe Benvenuto, LIFTbuild COO. “Some of [that] came from the warehouse facility that we had built and rented for staging and pre-fabrication. The roof is a good example. All of that membrane went on, all the rooftop equipment [installation work] is happening on site but before it’s lifted into place. All of the penthouse roofs were assembled, membrane put on, and all of that done at grade.”

Another prefabricated component was framing. LIFTbuild worked with Exchange architect Ghafari on modeling the wall framing down to the level of each screw and then roll-forming all of the studs.

Benvenuto said getting all project team members comfortable with the idea of a DfMA workflow is the most important part of getting the real efficiency savings out of the process.

Prefabricated exterior panels
Prefabricated exterior panels
Prefabricated exterior panels

Prefabricated exterior panels were built in a LIFTbuild offsite facility and delivered ready to install to the Exchange site in Detroit.
Photos courtesy Liftbuild

“We’ll take the program of the building, the documents, and this is usually happening in the schematic design phase, so we have an opportunity to change design if needed to support a prefabrication effort,” explains Benvenuto. “You get into this mix of waiting until the design is done to make these decisions, then sometimes the design could potentially need to be changed to accommodate prefabrication goals. So there’s a right time to do it. I think [when the] schematic is just getting into design development-level documents is the right time to do it.”

Benvenuto says laying out a strategy and going through a workshop with all of the subcontractors to identify opportunities to perform work earlier in the sequence—such as the roof membranes and framing—helped out enormously on Exchange, which was itself a pilot project for the LIFTbuild system.

“We kind of put together action plans where we’d sit down with an architect, and need to address prefabrication strategy with [them], with the engineer,” he adds. “If there were no issues with designing things the way we normally would, if this was solely a means and methods, meaning the design can continue to go down the road as it is, then it would.”

LIFTbuild is currently exploring opportunities in both multifamily residential and health care for its second U.S. project. As with WSP and Mace, the process efficiencies of DfMA have excited the LIFTbuild team.

“We have tried to remodel that whole design lifecycle because of the way our building is built,” says Benvenuto. “When you design for more of a manufacturing environment or DfMA, it’s a whole different level. I think the sooner we align the objectives of construction with the objectives of design, the better off we will be.”