In just 12 days and one hour, the project team planned and executed the complete replacement of two vertical 60-ton feed water heaters at the Oconee Nuclear Station, which power nearly 2 million homes in the region.
TK Elevator’s new, 216,292-sq-ft home for research, testing and training changed the skyline in Cobb County as its tallest building and the tallest test tower in the United States at more than 420 feet tall.
Completed in June 2021, Sun Streams 2 is a 200-MW solar facility located approximately 40 miles west of Phoenix that will power new energy-efficient data centers being built by Microsoft Corp. in nearby Goodyear and El Mirage.
The project team was hired to build a 138/23-kV gas-insulated substation and associated infrastructure in the heart of Pittsburgh for electric utility Duquesne Light.
The $1.4-billion expansion of a Phillips 66 natural gas liquids complex in Sweeny, Texas, was “the best example of teamwork I have seen in my 30-plus year career,” says John Parker, senior vice president of construction at project design-builder S&B Engineers and Constructors.
The $39-million Diamond Green Diesel No. 2 Plant Expansion was designed to more than double the capacity of renewable diesel at DGD’s Norco, La., refinery.
The $1.4-billion expansion of the Phillips 66 natural gas liquids complex in Sweeny, Texas, transformed the facility into one of the nation’s largest NGL processing hubs and quadrupled the site’s capacity.
Red Rock Dam, a U.S. Army Corps of Engineers facility on the Des Moines River near Pella, Iowa, got a new powerhouse courtesy of Stantec’s design and a new generation license from the Federal Energy Regulatory Commission.