Work was suspended on the project's cable-stayed portion based on unspecified safety concerns over the planned installation of some bridge structure elements.
The joint venture will complete engineering work on the new $930-million U.S. Route 181/Harbor Bridge in Texas, taking over from original engineer-of-record FIGG.
More than six months after design work was halted on its signature cable-stayed main spans, construction of the new Harbor Bridge in Corpus Christi, Texas, has pressed ahead, even as uncertainties shroud its ultimate cost and completion schedule.
A joint venture made up of Flatiron Construction Corp., Skanska, and Stacy and Witbeck (FSSW), was recently awarded an additional segment on the North Coast Corridor project in San Diego County.