I'd like to make a few unmade points about “A Cautionary Digital Tale of Virtual Design and Construction,” the story run by ENR and ENR.com last month that drew 100 comments.
The story discusses “the first known claim related to the use of building information modeling by an architect ... [who] used BIM to fit the building's MEP systems into the ceiling plenum ... [but] did not tell the contractor that the extremely tight fit, coordinated in the BIM, depended on a very specific installation sequence.”
Typically, any first year law student would tell us that the owner cannot both tell the contractor what to do and how to do it, and then expect the contractor to be responsible for the results. Even suggesting “one possible way” to accomplish an end will be interpreted by a court to mean the contractor may rely on such suggestion.
This is often referred to as the Spearin doctrine.
According to the Industrial Risk Management Institute, Spearin is a legal principle that holds that when a contractor follows the plans and specifications furnished by the owner, and those plans and specifications turn out to be defective or insufficient, the contractor is not liable to the owner for any loss or damage resulting from the defective plans and specifications. This rule has been adopted by the courts in virtually all states.
Control and responsibility are linked.
Because of Spearin, the engineer's "mock CPM" should not be shared with the contractor.
BIM modeling not only permits, but encourages “fit out” studies.
Designers previously leaving large tolerances in a utility chase, so to insure against their implied guarantee that “all can fit”, now are going to the next level of coordination and reducing wasted space to a minimum.
If the engineer only has raw boring data, it need not prepare and share the analysis thereof. If the engineer only has a BIM model having tolerant utility chases, it need not prepare and share a coordination analysis.
But if the analyses are performed, and especially where the final design depends on these studies, they must be shared and highlighted so as to not be lost in the haystack.
As we move to a world of more collaboration, even among contractual adversaries, the impact of a shared computer in the office of the engineer, or in the Cloud, must be considered.
Contemplate a 3D 4D 5D BIM model (which may be viewed from a new angle by the contractor revealing construction or even end user functionality issues) or resource loaded and leveled CPM schedule (which may reveal to the owner that a subcontractor working on other owner works is now dangerously over-extended).
The owner approved the contractor’s submitted subcontractor. Now the owner has additional information.
Does the owner of 2011 have the duty (or the right) to notify the contractor that the subcontractor is not getting its submitted estimated CPM durations on other works on the site?
Does the contractor of 2011 have the duty to notify the owner that it can install a valve, but it will be inaccessible to the owner’s maintenance personnel?