The National Nuclear Security Administration’s harshly worded rejection of up to $2.7 million in performance bonuses for 2016 construction progress at the Mixed-Oxide Fuel Fabrication Facility project in Aiken, S.C., has prompted a fiery rebuttal from contractor CB&I Areva MOX Services.
An ongoing political battle between the Obama administration and Congress over construction of the budget-busting Mixed Oxide Fuel Fabrication Facility in South Carolina heated up after Oct. 3, when Vladimir Putin announced that Russia is suspending its participation in the international treaty governing plutonium disposition that served as the project’s impetus.