Ruling largely rejects state assertion that challenge of Transurban/Macquarie contract missed key deadline; no state comment yet on impact to project schedule.
Purple Line's new JV contractor Dragados-OHL will start in spring as state approves its contract on Jan. 26. Construction tab now is $3.4B, with opening four years past original estimate, say officials.
It's not clear why one team opted out of competition for the estimated $11 billion I-270/Beltway expansion in a major commuter corridor outside Washington, D.C.
Following state suit, judge issues TRO to keep concession and builders working on $2B rail project through mid-Sept. as delay liability talks continue.
The design-build phase of the $2.1- billion Elizabeth River Tunnels project in Norfolk, Va., finished last month—one year ahead of schedule—in a P3 collaboration between a Skanska USA-Kiewit-Weeks Marine Inc. team and the Virginia Dept. of Transportation.