April 2019
Related Article:
Industrial, Roadway Projects Lead Top Starts Ranking
Click below for earlier editions:
2017 | 2016 | 2015
Rank |
Project/ Location |
Project Cost ($ Mil.) |
Start Date/ End Date |
Owner/Developer |
Team |
---|---|---|---|---|---|
1
|
PROPYLENE OXIDE & TERTIARY BUTYL ALCOHOL
CHEMICAL PLANT Channelview, Texas |
2,400
|
Aug. 2018
2021 |
LyondellBassell Corp. |
Project Manager: Worley Parsons Engineer: Fluor Corp. |
2
|
GRAY OAK PIPELINE Orla to Corpus Christi/Ingleside to Sweeny, Texas |
2,000
|
Aug. 2018
2019 |
Phillips 66/Andeavor Corp.
(Formerly Tesoro)
|
Contractor/Engineer: Phillips 66
|
3
|
GULF COAST EXPRESS PIPELINE Waha to Agua Dulce, Texas |
1,750
|
May 2018
Oct. 2019 |
Kinder Morgan Operating
Energy Partners/DCP Midstream
Co./Targa Resources LP
|
Contractor/Design: Morgan Operating
Energy Partners |
4
|
TOTAL PETROCHEM PLANT EXPANSION & ETHANE
STEAM CRACKER PLANT Port Arthur, Texas |
1,700
|
June 2018
2020 |
Total Petrochemicals USA Inc.
|
GC: McDermott Inc.
Engineer: CB&I/McDermott Inc. |
5
|
BOIS D’ARC LAKE Fannin County, Texas |
1,600
|
May 2018
March 2022 |
North Texas Municipal Water
District
|
CMAR: Archer Western; Garney Construction; Austin
Bridge & Road
Design: Freese and Nichols Inc.; Jacobs Engineering; Black & Veach; CP&Y; AECOM; HDR; Pacheco Koch; White Hawk; Bridgefarmer |
6
|
PHILLIPS 66 NGL FRACTIONATORS (EXPANSION) Old Ocean (Sweeny Hub), Texas |
1,500
|
June 2018
2020 |
Phillips 66
|
Contractor/Engineer: S & B Engineers &
Constructors Ltd.
|
7
|
ARBUCKLE II NATURAL GAS PIPELINE Oklahoma to Texas |
1,360
|
Sept. 2018
2020 |
Oneok Partners Inc.
|
Construction Manager/Design: Oneok Partners Inc.
|
8
|
GRAND PRIX NGL PIPELINE Permian Basin to Mont Belvieu, Texas |
1,300
|
Feb. 2018
Q4 2019 |
Targa Resources LP
|
GC/Design: Targa Resources LP
|
9
|
CACTUS II PIPELINES Wink to McCamey to Corpus Christi, Texas |
1,100
|
Jan. 2018
Q3 2019 |
Plains All American Pipeline LP
|
Engineer: Plains All American Pipeline LP
|
10
|
TWIN SHIP CHANNEL BRIDGE Pasadena, Texas |
962
|
March 2018
2024 |
Harris County Toll Road
Authority
|
GC: Ship Channel Constructors, JV of Traylor Bros Inc.
and Zachry Construction Corp.
Civil Design: Dannenbaum Engineering Corp. |
11
|
ENTERGY LAKE CHARLES POWER STATION Westlake, La. |
872
|
Jan. 2018
June 2020 |
Entergy Louisiana LLC
|
GC/Design: CB&I Environmental and Infrastructure
|
12
|
GRAND PARKWAY SEGMENTS H AND I-1 Texas |
855
|
March 2018
Q1 2022 |
Texas Dept. of Transportation
|
GC: Webber LLC/Granite Construction Co./Ferrovial
Agroman US Corp.
|
13
|
BAYOU BRIDGE CRUDE OIL PIPELINE PHASE II
Lake Charles to St. James, La. |
750 |
Jan. 2018
Q1 2019 |
Energy Transfer Partners LP/
Phillips 66
|
GC: Stupp Corp./Sunland Construction/TRC Solutions
|
14
|
SOUTHERN GATEWAY (I-35/US 67) Dallas |
666
|
Feb. 2018
2021 |
Texas Dept. of Transportation
|
GC: Pegasus Link Constructors, JV of Fluor
Enterprises Inc. and Balfour Beatty Inc.
|
15
|
KALAHARI RESORTS ROUND ROCK Round Rock, Texas |
550
|
May 2018
Nov. 2020 |
Kalahari Resort
|
GC: Hensel Phelps Construction/TEDCO Construction Corp.
Design: HKS Inc. |
15
|
UNION PACIFIC BRAZOS RAILROAD YARD Hearne, Texas |
550
|
Jan. 2018
2020 |
Union Pacific Railroad
|
GC: Ragnar Benson Construction LLC
Design: HDR Engineering |
17
|
FOUR SEASONS HOTEL (REDEVELOPMENT OF OLD
WORLD TRADE CENTER) New Orleans |
470
|
June 2018
Jan. 2021 |
Two Canal Owner/Carpenter &
Co. and Woodward Interests
|
GC: Woodward Tishman, Joint Venture
Design: Cambridge Seven Associates Inc./ Woodward Design Group/Trapolin-Peer Architects |
18
|
EASTERN OKLAHOMA COUNTY CORRIDOR Eastern Oklahoma County, Okla. |
449
|
Jan. 2018
2020 |
Oklahoma Turnpike Authority
|
Program Manager: Poe & Associates
Engineers: Olsson Associates; CEC; MacArthur Associated Consultants; MKEC; Atkins |
19
|
I-635/SH 121 INTERCHANGE IMPROVEMENT Dallas |
370
|
Aug. 2018
2022 |
Texas Dept. of Transportation
|
GC: NorthGate Constructors
|
20
|
SOFIDEL AMERICA PAPER FACTORY Inola, Okla. |
360
|
March 2018
Q2 2020 |
Sofidel of America
|
GC/Design: Gray
|
21
|
OKLAHOMA CITY MAPS 3 CONVENTION CENTER Oklahoma City |
288
|
June 2018
2020 |
Oklahoma City Public Works
|
GC: Flintco LLC/Tulsa Vision Builders
Design: Populous Architects PC |
22
|
IH 10 LANE IMPROVEMENT Yoakum, Texas |
279.1
|
Nov. 2018
May 2023 |
Texas Dept. of Transportation
|
GC: Webber LLC
|
23
|
5TH & BRAZOS (RESIDENTIAL/HOTEL TOWER) Austin |
272.1
|
Dec. 2018
2020 |
Magellan Development Group
Ltd.
|
GC: Ryan Cos. South Central Region
Design: bKL Architecture LLC |
24
|
MIDWAY SOLAR GENERATING FACILITY Fort Stockton, Texas |
260
|
Jan. 2018
Early 2019 |
174 Power Global Corp.
|
Builder/Developer: 174 Power Global Corp.
|
25
|
JSW MELT AND MANUFACTURE STEEL PLATE MILL Baytown, Texas |
250
|
Oct. 2018
2020 |
JSW Group
|
GC/Design: JSW Group
|
26
|
OMNI OKLAHOMA CITY HOTEL Oklahoma City |
241
|
Sept. 2018
Dec. 2020 |
TRT Holdings Inc.
|
GC: Brasfield & Gorrie
Design: Rule Joy Trammell + Rubio LLC |
27
|
BITMAIN BLOCKCHAIN DATA CENTER & MINING
FACILITY - PHASE 1 Rockdale, Texas |
232.5
|
Aug. 2018
2019 |
Bitmain Technologies Ltd.
|
Owner’s Agent: Edelman
|
28
|
IH 45 ROAD IMPROVEMENTS Houston |
230.5
|
July 2018
July 2022 |
Texas Dept. of Transportation
|
GC: Williams Bros. Construction Co.
|
29
|
CPS ENERGY HEADQUARTERS San Antonio |
210
|
Jan. 2018
June 2020 |
CPS Energy
|
GC: Sundt Construction
Design: Corgan Associates Inc. |
30
|
ROCK HILL HIGH SCHOOL Prosper, Texas |
208.4
|
May 2018
May 2020 |
Prosper Independent School
District
|
GC: Pogue Construction
Design: Huckabee |
31
|
MILL CREEK/PEAKS BRANCH/STATE-THOMAS
DRAINAGE RELIEF TUNNEL PROJECT Dallas |
206.7
|
March 2018
2023 |
City of Dallas Business Dev. &
Procurement Services/City of
Dallas Trinity River Management
|
GC: Southland/Mole JV
|
32
|
SH 365 TOLLWAY - PHASE II (SEGMENTS 1 & 2) Pharr, Texas |
202.5
|
July 2018
2022 |
Hidalgo County Regional
Mobility Authority
|
GC: Johnson Bros. Corp., a Southland Co.
|
33
|
SH 146 (NASA 1 TO HARRIS/GALVESTON COUNTY LINE) Harris County, Texas |
201.8
|
Aug. 2018
Aug. 2023 |
Texas Dept. of Transportation
|
GC: Webber LLC
|
34
|
NATURAL GAS GATHERING SYSTEM & CRYOGENIC
GAS PROCESSING PLANT Arkoma, Okla. |
200
|
Feb. 2018
2020 |
Valiant Midstream LLC
|
GC/Design: Valiant Midstream LLC
|
35
|
BUREAU OF ENGRAVING/PRINTING WESTERN
CURRENCY FACILITY EXPANSION Fort Worth |
196.3
|
Oct. 2018
Jan. 2022 |
US Army Corps of Engineers
|
GC: Hensel Phelps Construction Co.
|
36
|
US 281 (STONE OAK TO BEXAR/COMAL COUNTY LINE) Bexar County, Texas |
178.4
|
Aug. 2018
Aug. 2022 |
Texas Dept. of Transportation
|
GC: Zachry Construction Corp.
|
37
|
300 COLORADO OFFICE TOWER Austin |
175
|
Nov. 2018
Dec. 2020 |
Cousins Properties/Ironwood
Real Estate/Riverside Resources
|
GC: DCA Construction/Holder Construction Co.
Design: Pickard Chilton/Kendall/Heaton Associates |
37
|
METHODIST MIDLOTHIAN MEDICAL CENTER Midlothian, Texas |
175
|
Oct. 2018
2020 |
Methodist Health System
(Dallas)
|
GC: DPR Construction Inc.
Design: Corgan Associates Inc. |
39
|
IH 820 Fort Worth |
173.7
|
Aug. 2018
2022 |
Texas Dept. of Transportation
|
GC: Flatiron Constructors Inc.
|
40
|
ENERGY ENGINEERING BUILDING
Austin |
160 |
Dec. 2018
May 2021 |
University of Texas Facilities &
Planning
|
Construction Manager: Beck Group
Design: Jacobs Engineering Group |
41
|
US62/180 (MONTANA AVENUE) El Paso, Texas |
144.2
|
Dec. 2018
Oct. 2021 |
Texas Dept. of Transportation
|
GC: Jordan Foster Construction LLC
|
42
|
ATELIER (MIXED-USE DEVELOPMENT) Dallas |
139.8
|
June 2018
March 2021 |
ZT Development/ZOM Living
|
GC: Balfour Beatty US
Design: Stantec |
43
|
COLLIN COLLEGE WYLIE CAMPUS Wylie, Texas |
131.4
|
Sept. 2018
June 2020 |
Collin College
|
GC: Skanska USA
Design: Page Southerland Page |
44
|
IH 10 WIDENING (FM 365 E TO CR 131) Jefferson County, Texas |
128.4
|
Aug. 2018
April 2023 |
Texas Dept. of Transportation
|
GC: Johnson Bros. Corp., a Southland Co.
|
45
|
THE ARTS RESIDENCES AT THE THOMPSON HOTEL San Antonio |
120
|
April 2018
May 2020 |
DC Partners USA
|
GC: Jordan Foster Construction LLC
Design: Powers Brown Architecture |
46
|
US 77 (FUTURE IH 69 LOOP AROUND DRISCOLL) Nueces County, Texas |
118.3
|
Aug. 2018
Feb. 2022 |
Texas Dept. of Transportation
|
GC: Zachry Construction Corp.
|
47
|
IH 610 (WEST OF CAMBRIDGE ST. TO WEST OF SCOTT ST.) Harris County, Texas |
116.9
|
Oct. 2018
March 2022 |
Texas Dept. of Transportation
|
GC: Williams Bros. Construction Co.
|
48
|
HIGH SCHOOL NO. 4 San Antonio |
109
|
April 2018
July 2020 |
Comal Independent School
District
|
GC: Bartlett Cocke General Contractors
Design: Huckabee |
49
|
IH 10 BEXAR COUNTY EXPANSION PROJECT San Antonio |
108.9
|
Oct. 2018
Feb. 2021 |
Texas Dept. of Transportation
|
GC: Webber LLC
|
50
|
THE ODEON AT SOUTH MARKET DISTRICT New Orleans |
105
|
July 2018
Sept. 2020 |
Domain Cos.
|
GC: Woodward Design+Build
Design: Humphreys & Partners Architects LP |
51
|
US 59 (CLEVELAND BYPASS TO MONTGOMERY COUNTY) Liberty County, Texas |
102.1
|
Oct. 2018
Nov. 2021 |
Texas Dept. of Transportation
|
GC: James Construction Group LLC
|
52
|
OLIVER PLACE Dallas |
100
|
April 2018
Dec. 2019 |
Southern Land Co.
|
GC: SLC Commercial Construction
Design: GDA Architects |
52
|
SOUTHERN POINTE COMMUNITY Texas |
100
|
March 2018
2030 |
Southern Pointe Community
|
Design/Construction: Jones|Carter
|
54
|
LIVE GRANDSCAPE The Colony, Texas |
95
|
Dec. 2018
July 2021 |
Lanoha Development
|
GC: VCC Construction
Design: Merriman Anderson Architects |
54
|
TEXAS CHRISTIAN UNIVERSITY – EAST SIDE
ADDITION OF AMON G. CARTER STADIUM Fort Worth |
95
|
May 2018
Aug. 2019 |
Texas Christian University
|
GC: Turner Construction Co.
Design: HKS Inc. |