Hoffman is in charge of building the Brightwater treatment plant. This year it plans to complete the buildings, backfill structures, build digesters, install mechanical and electrical systems (pumps, piping, ducts), and begin landscaping.
IMAGE COURTESY OF KING COUNTY SOLIDS STREAM
IMAGE COURTESY OF KING COUNTY) DIGESTERS
Key Players
Project Name: Brightwater Treatment Plant Main facility
Location: Bothell Wash.
Total Construction Cost: $73 million
Construction Start Date: 2007
Construction End Date: 2010
General Contractor: Hoffman Construction
Subcontractors: University Mechanical